For a project, an estimated normal time with an associated normal cost is given for each activity. Crash times, the minimum duration required to complete each activity, and their associated crash costs are also given. Draw the AON diagram. Determine the ES, EF, LS, LF times and critical path. Crash the project to 12 weeks by explaining each crashing step. Determine the total project cost after crashing. Time (weeks) Cost (in $) Feasible Immediate time reduction Crash Activity Normal Crash Normal Crash CP? Predecessors in weeks cost/week А 40000 40000 B 3 48000 56000 C В 4 2 80000 88000 D А, С 4 55000 56000 E В 9 7 90000 96000 F C 6 78000 84000 G D, F 2 1 25000 32000 H E, G 1 1 15000 15000 B.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Can you solve this question please

For a project, an estimated normal time with an associated normal cost is given for each activity. Crash
times, the minimum duration required to complete each activity, and their associated crash costs are also
given. Draw the AON diagram. Determine the ES, EF, LS, LF times and critical path.
Crash the project to 12 weeks by explaining each crashing step. Determine the total project cost after
crashing.
Time (weeks)
Cost (in $)
Feasible
Immediate
time reduction
Crash
Activity
Normal
Crash
Normal
Crash
СР?
Predecessors
in weeks
cost/week
A
2
2
40000
40000
2
48000
56000
В
4
2
80000
88000
D
A, C
4
55000
56000
E
В
9.
7
90000
96000
F
C
6.
78000
84000
G
D, F
1
25000
32000
H
Е, G
1
1
15000
15000
B.
B.
Transcribed Image Text:For a project, an estimated normal time with an associated normal cost is given for each activity. Crash times, the minimum duration required to complete each activity, and their associated crash costs are also given. Draw the AON diagram. Determine the ES, EF, LS, LF times and critical path. Crash the project to 12 weeks by explaining each crashing step. Determine the total project cost after crashing. Time (weeks) Cost (in $) Feasible Immediate time reduction Crash Activity Normal Crash Normal Crash СР? Predecessors in weeks cost/week A 2 2 40000 40000 2 48000 56000 В 4 2 80000 88000 D A, C 4 55000 56000 E В 9. 7 90000 96000 F C 6. 78000 84000 G D, F 1 25000 32000 H Е, G 1 1 15000 15000 B. B.
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Valuing Decision
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education