Following Diagram explaination is
Task A, duration 2, no dependency
Task B, duration 4, no dependency
Task C, duration 7, no dependency
Task D, duration 5, depends on Task A
Task E, duration 3, depends on Task B and Task C
Task F, duration 8, depends on Task C
Task G, duration 10, depends on Task D and Task E
Task H, duration 4, depends on Task E
Task I, duration 7, depends on Task F
Task J, duration 12, depends on Task H and Task I
So question is
adjust
the durations using PERT calculation from the
three-point estimates below and recalculate slack.
Task A, Optimistic = 1, Normal = 2, Pessimistic = 5
Task B, Optimistic = 2, Normal = 4, Pessimistic = 8
Tack C, Optimistic = 3, Normal = 7, Pessimistic = 12
Task D, Optimistic = 3, Normal = 5, Pessimistic = 10
Task E, Optimistic = 1, Normal = 3, Pessimistic = 6
Task F, Optimistic = 3, Normal = 8, Pessimistic = 15
Task G, Optimistic = 7, Normal = 10, Pessimistic = 22
Task H, Optimistic = 3, Normal = 4, Pessimistic = 6
Task I, Optimistic = 5, Normal = 7, Pessimistic = 12
Task J, Optimistic = 10, Normal = 12, Pessimistic = 15
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 5 images
- Bonus Allocation: To determine the allocation of the $30,000 bonus among the employees (Kaleb, Daphane, and Max), we need to consider various factors such as their overall performance, goal achievements, and individual contributions. Here's a possible distribution based on the provided information: a. Kaleb (Senior Web Developer): Performance and goal achievement: Alice demonstrated excellent technical skills and made significant progress in improving her time management, surpassing the initial goal. b. Contribution: She has been involved in several successful client projects and has excellent communication and collaboration skills. c. Daphane (Project Manager): Performance and goal achievement: Bob showed growth in adapting his leadership style and achieved a higher level of employee satisfaction than the targeted goal. d. Contribution: He successfully managed projects, delivered them on time and within budget, and maintained positive client relationships. e. Max…arrow_forwardHow can a work breakdown structure contribute to scope creep prevention?arrow_forward2arrow_forward
- Activity Immediate Predecessors Normal Time (NT) (weeks) Normal Cost (NC) ($) Crash Time (CT) (weeks) Crash Cost (NC) ($) A --- 4 $200 2 $650 B A 6 $500 4 $900 C A 5 $600 3 $1,200 D A 6 $1000 5 $1,400 E B 6 $1,500 5 $2,000 F C, D 5 $200 4 $400 G E, F 6 $600 4 $1200 Determine the minimum cost-schedule for this project to be completed in 18 weeks.?arrow_forwardActivity Normal_time Crash_time Normal_cost Crash_cost Slack 28 22 5800 6700 0 30 4200 4200 1 13 4500 4500 0 25 4300 6700 1 18 5700 6700 2 20 5200 6500 2 AB C D E F 30 13 33 29 Previous 34 The table shows normal time (in days), crash time (in days), normal cost (in dollars), crash cost (in dollars) and slack time (in days) of activities in a small construction project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity, Example: A. Nextarrow_forwardPractice Problem #1 A process consists of 30 activities E task time = 42 min/unit Longest activity = 2.4 min Shortest activity = 0.3 min Available Time, A = 480 min/day (A) Max cycle time = Min cycle time = YC) If cycle time = 42 min, R = (D) If cycle time = 2.4 min, R = (E) If number of workstations, N = 10, and cycle time is 4.2 min/unit %3D Output Rate, R = (F) Assembly-line Efficiency =arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.