Find the critical path of the activity network below. (SHOW COMPLETE SOLUTION AND ILLUSTRATION ON HOW YOU GOT IT) Immedlate Estimated Activity Activity Description Predecessors Duration A Excavate 2 weeks | Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting B A 4 weeks C B 10 weeks 6 weeks E 4 weeks 5 weeks 7 weeks E D E, G 9 weeks Do the electrical work C 7 weeks Put up the wallboard Install the flooring Do the interior painting F,I 8 weeks 4 weeks 5 weeks M Install the exterior fixtures H 2 weeks N Install the interior fixtures K, L 6 weeks Total = 79 weeks

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

pllss i need the answerr30 mins left

Find the critical path of the activity network below.
(SHOW COMPLETE SOLUTION AND ILLUSTRATION ON HOW YOU GOT IT)
Immediate
Estimated
Activity
Activity Description
Predecessors
Duration
A
Excavate
2 weeks
Lay the foundation
Put up the rough wall
Put up the roof
Install the exterior plumbing
Install the interior plumbing
Put up the exterior siding
Do the exterior painting
B
A
4 weeks
10 weeks
C
6 weeks
4 weeks
5 weeks
7 weeks
E
F
E
D
E, G
9 weeks
Do the electrical work
C
7 weeks
Put up the wallboard
Install the flooring
Do the interior painting
Install the exterior fixtures
F, I
8 weeks
K
4 weeks
5 weeks
M
H
2 weeks
N
Install the interior fixtures
K, L
6 weeks
Total = 79 weeks
Transcribed Image Text:Find the critical path of the activity network below. (SHOW COMPLETE SOLUTION AND ILLUSTRATION ON HOW YOU GOT IT) Immediate Estimated Activity Activity Description Predecessors Duration A Excavate 2 weeks Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting B A 4 weeks 10 weeks C 6 weeks 4 weeks 5 weeks 7 weeks E F E D E, G 9 weeks Do the electrical work C 7 weeks Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures F, I 8 weeks K 4 weeks 5 weeks M H 2 weeks N Install the interior fixtures K, L 6 weeks Total = 79 weeks
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
System of units
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning