Question

Fin-Click Solutions is a software development company. It is specialized in developing software for financial institutions. Fin-Click is running an online banking mobile application project for AtoZ bank. The followings are the activities for implementing the project which is named iMoney. Salem Ali, the project manager, is a professional project manager and has over 20 years of experience in his field. The following table presents a proposed set of activities with their estimated durations based on his previous experience with another similar project.

 

Activity Code

Activity Name

Activity Duration

(in days)

Dependency

A

Define New Business Rules

14

-

B

Define Specific UI Requirements

9

A

C

Define Functional Specifications

20

A

D

Create Code Design Document

14

B

E

Implement Code Control System

20

D,F

F

Setup Development Environment

10

A

G

UI Development

25

E

H

Code Development

50

F

I

Test Environment Setup

15

H

J

Test Plan

10

G,I

K

Unit Testing

20

H

L

UAT

15

C,H

M

Results Reporting

7

J,K,L

N

Operations Switch Over

5

M

 

 

 

 

 

 

Based on the given information answer the following:

1. Draw a network diagram for iMoney project using the precedence diagraming method. 
2. How many paths are there in this project? List them with the duration of each.
3. What is the overall duration of the iMoney project? 
4. What is the Critical Path(s) of the project? 
5. What is the total and free slacks of iMoney project? Show your work on the diagram.
6. Although the development team claimed that the time given for setting up the development environment is sufficient, the project manager was not confident from that claim and he placed 2 extra weeks as a contingency. The project manager also added three more contingency days just in case other tasks may slip the schedule. 
a. Show the effect of these provisions on the network diagram and recalculate the overall duration of the project after introducing these changes.
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Database System Concepts
Computer Science
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:McGraw-Hill Education
Text book image
Starting Out with Python (4th Edition)
Computer Science
ISBN:9780134444321
Author:Tony Gaddis
Publisher:PEARSON
Text book image
Digital Fundamentals (11th Edition)
Computer Science
ISBN:9780132737968
Author:Thomas L. Floyd
Publisher:PEARSON
Text book image
C How to Program (8th Edition)
Computer Science
ISBN:9780133976892
Author:Paul J. Deitel, Harvey Deitel
Publisher:PEARSON
Text book image
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781337627900
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning
Text book image
Programmable Logic Controllers
Computer Science
ISBN:9780073373843
Author:Frank D. Petruzella
Publisher:McGraw-Hill Education