Concept explainers
During 2020, Skysong Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available.
2020
|
2021
|
2022
|
||||
---|---|---|---|---|---|---|
Costs incurred to date
|
$383,800 | $850,200 | $1,074,000 | |||
Estimated costs to complete
|
626,200 | 239,800 | –0– | |||
Billings to date
|
300,000 | 899,000 | 1,620,000 | |||
Collections to date
|
267,000 | 816,000 | 1,429,000 |
Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
|
||
---|---|---|
Gross profit recognized in 2021
|
||
Gross profit recognized in 2022
|
Prepare all necessary
Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
- In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).2-c. In the journal below, complete the necessary journal entries for the year 2023…arrow_forwardDuring 2020, Grouper Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $370,000 $869,790 $1,080,000 Estimated costs to complete 630,000 231,210 –0– Billings to date 302,000 900,000 1,590,000 Collections to date 267,000 804,000 1,415,000 (a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount Gross profit recognized in 2021 $enter a dollar amount Gross profit recognized in 2022 $enter a dollar amountarrow_forwardDuring 2023, Sunland Company started a construction job with a contract price of $1,792,000. The job was completed in 2025. The following information is available. The contract is non-cancellable. Costs incurred to date Estimated costs to complete Billings to date (non-refundable) Collections to date (a) 2023 2024 $448,000 $924,000 672,000 336,000 1,008,000 907,200 302.400 308,000 0000 2025 $1,198,400 0 1,792,000 1,596,000 Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) nont ROOFarrow_forward
- Explain clearlyarrow_forwardHi can someone help me with this question please?arrow_forwardOn January 1, 2022, Winter Harvest Ltd. started a construction project for $4,500,000. Relevant data for 2022 and 2023 are as follows: 2022 2023 Current year construction costs $ 3,300,000 $ 620, 000 Estimated remaining costs to complete 600,000 - 0- Current year billings 3, 100, 000 1,400,000 Current year collections 3,000,000 1,500, 000 Required 1. Calculate the following amounts for each method: 2. Completed Contract Percentage of Completion 2022 2023 2022 2023 Gross Profit $ ? $ ? $ ? $ ? Construction in progress year - end balance. $ ? $ ? $ ? $ ? Costs in excess of billi\table[[, \table[[Completed], [Contract]], \table[[Percentage of], [Completion]]], [, 2022, 2023, 2022, 2023], [Gross Profit,$?, $?, $ ?, $?ngs (Billings in excess of costs) $ ? $ ? $ ? $ ?arrow_forward
- Answer is $1,800,000. Please explain the reasoning and calculationsarrow_forwardDuring 2020, Teal Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $889,380 $1,061,000 Estimated costs to complete 616,100 208,620 -0- Billings to date 303,000 902,000 1,620,000 Collections to date 273,000 814,000 1,418,000 (a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized in 2021 $ Gross profit recognized in 2022 %24 %24arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education