Direct Materials Purchases Budget: Direct Labor Budget Crescent Company produces stuffed toy animals; one of these is “Arabeau the Cow.” Each Arabeau takes 0.20 yard of fabric (white with irregular black splotches) and 10 ounces of polyfiberfill. Fabric costs $3.40 per yard and polyfiberfill is $0.05 per ounce. Crescent has budgeted production of Arabeaus for the next four months as follows:   Units October 44,000 November 80,000 December 50,000 January 40,000 Inventory policy requires that sufficient fabric be in ending monthly inventory to satisfy 20 percent of the following month’s production needs and sufficient polyfiberfill be in inventory to satisfy 40 percent of the following month’s production needs. Inventory of fabric and polyfiberfill at the beginning of October equals exactly the amount needed to satisfy the inventory policy. Each Arabeau produced requires (on average) 0.10 direct labor hour. The average cost of direct labor is $15 per hour. Required: 1. Prepare a direct materials purchases budget of fabric for the last quarter of the year showing purchases in units and in dollars for each month and for the quarter in total. Round your answers to the nearest cent, if required. Crescent Company Direct Materials Purchases Budget for Fabric For the Fourth Quarter   October November December Total Units produced fill in the blank 4450adfc9005f82_1 fill in the blank 4450adfc9005f82_2 fill in the blank 4450adfc9005f82_3 fill in the blank 4450adfc9005f82_4 DM per unit (yd.) fill in the blank 4450adfc9005f82_5 fill in the blank 4450adfc9005f82_6 fill in the blank 4450adfc9005f82_7 fill in the blank 4450adfc9005f82_8 Production needs fill in the blank 4450adfc9005f82_9 fill in the blank 4450adfc9005f82_10 fill in the blank 4450adfc9005f82_11 fill in the blank 4450adfc9005f82_12 Desired ending inventory (yd.) fill in the blank 4450adfc9005f82_13 fill in the blank 4450adfc9005f82_14 fill in the blank 4450adfc9005f82_15 fill in the blank 4450adfc9005f82_16 Total needed fill in the blank 4450adfc9005f82_17 fill in the blank 4450adfc9005f82_18 fill in the blank 4450adfc9005f82_19 fill in the blank 4450adfc9005f82_20 Less: Beginning inventory fill in the blank 4450adfc9005f82_21 fill in the blank 4450adfc9005f82_22 fill in the blank 4450adfc9005f82_23 fill in the blank 4450adfc9005f82_24 DM to be purchased (yd.) fill in the blank 4450adfc9005f82_25 fill in the blank 4450adfc9005f82_26 fill in the blank 4450adfc9005f82_27 fill in the blank 4450adfc9005f82_28 Cost per yard $fill in the blank 4450adfc9005f82_29 $fill in the blank 4450adfc9005f82_30 $fill in the blank 4450adfc9005f82_31 $fill in the blank 4450adfc9005f82_32 Total purchase cost $fill in the blank 4450adfc9005f82_33 $fill in the blank 4450adfc9005f82_34 $fill in the blank 4450adfc9005f82_35 $fill in the blank 4450adfc9005f82_36   2. Prepare a direct materials purchases budget of polyfiberfill for the last quarter of the year showing purchases in units and in dollars for each month and for the quarter in total. Round your answers to the nearest cent, if required. Crescent Company Direct Materials Purchases Budget for Polyfiberfill For the Fourth Quarter   October November December Total Units produced         DM per unit (oz.)         Production needs         Desired ending inventory (oz.)         Total needed         Less: Beginning inventory         DM to be purchased (oz.)         Cost per ounce         Total purchase cost           3. Prepare a direct labor budget for the last quarter of the year showing the hours needed and the direct labor cost for each month and for the quarter in total. Round your answers to the nearest cent, if required. Crescent Company Direct Labor Budget For the Fourth Quarter   October November December Total Units produced         Direct labor time per unit (hours)         Direct labor hours needed         Cost per direct labor hour         Total direct labor cost

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter8: Budgeting For Planning And Control
Section: Chapter Questions
Problem 17E: Crescent Company produces stuffed toy animals; one of these is Arabeau the Cow. Each Arabeau takes...
icon
Related questions
icon
Concept explainers
Question

Direct Materials Purchases Budget: Direct Labor Budget

Crescent Company produces stuffed toy animals; one of these is “Arabeau the Cow.” Each Arabeau takes 0.20 yard of fabric (white with irregular black splotches) and 10 ounces of polyfiberfill. Fabric costs $3.40 per yard and polyfiberfill is $0.05 per ounce. Crescent has budgeted production of Arabeaus for the next four months as follows:

  Units
October 44,000
November 80,000
December 50,000
January 40,000

Inventory policy requires that sufficient fabric be in ending monthly inventory to satisfy 20 percent of the following month’s production needs and sufficient polyfiberfill be in inventory to satisfy 40 percent of the following month’s production needs. Inventory of fabric and polyfiberfill at the beginning of October equals exactly the amount needed to satisfy the inventory policy.

Each Arabeau produced requires (on average) 0.10 direct labor hour. The average cost of direct labor is $15 per hour.

Required:

1. Prepare a direct materials purchases budget of fabric for the last quarter of the year showing purchases in units and in dollars for each month and for the quarter in total. Round your answers to the nearest cent, if required.

Crescent Company
Direct Materials Purchases Budget for Fabric
For the Fourth Quarter
  October November December Total
Units produced fill in the blank 4450adfc9005f82_1 fill in the blank 4450adfc9005f82_2 fill in the blank 4450adfc9005f82_3 fill in the blank 4450adfc9005f82_4
DM per unit (yd.) fill in the blank 4450adfc9005f82_5 fill in the blank 4450adfc9005f82_6 fill in the blank 4450adfc9005f82_7 fill in the blank 4450adfc9005f82_8
Production needs fill in the blank 4450adfc9005f82_9 fill in the blank 4450adfc9005f82_10 fill in the blank 4450adfc9005f82_11 fill in the blank 4450adfc9005f82_12
Desired ending inventory (yd.) fill in the blank 4450adfc9005f82_13 fill in the blank 4450adfc9005f82_14 fill in the blank 4450adfc9005f82_15 fill in the blank 4450adfc9005f82_16
Total needed fill in the blank 4450adfc9005f82_17 fill in the blank 4450adfc9005f82_18 fill in the blank 4450adfc9005f82_19 fill in the blank 4450adfc9005f82_20
Less: Beginning inventory fill in the blank 4450adfc9005f82_21 fill in the blank 4450adfc9005f82_22 fill in the blank 4450adfc9005f82_23 fill in the blank 4450adfc9005f82_24
DM to be purchased (yd.) fill in the blank 4450adfc9005f82_25 fill in the blank 4450adfc9005f82_26 fill in the blank 4450adfc9005f82_27 fill in the blank 4450adfc9005f82_28
Cost per yard $fill in the blank 4450adfc9005f82_29 $fill in the blank 4450adfc9005f82_30 $fill in the blank 4450adfc9005f82_31 $fill in the blank 4450adfc9005f82_32
Total purchase cost $fill in the blank 4450adfc9005f82_33 $fill in the blank 4450adfc9005f82_34 $fill in the blank 4450adfc9005f82_35 $fill in the blank 4450adfc9005f82_36
 

2. Prepare a direct materials purchases budget of polyfiberfill for the last quarter of the year showing purchases in units and in dollars for each month and for the quarter in total. Round your answers to the nearest cent, if required.

Crescent Company
Direct Materials Purchases Budget for Polyfiberfill
For the Fourth Quarter
  October November December Total
Units produced        
DM per unit (oz.)        
Production needs        
Desired ending inventory (oz.)        
Total needed        
Less: Beginning inventory        
DM to be purchased (oz.)        
Cost per ounce        
Total purchase cost        
 

3. Prepare a direct labor budget for the last quarter of the year showing the hours needed and the direct labor cost for each month and for the quarter in total. Round your answers to the nearest cent, if required.

Crescent Company
Direct Labor Budget
For the Fourth Quarter
  October November December Total
Units produced        
Direct labor time per unit (hours)        
Direct labor hours needed        
Cost per direct labor hour        
Total direct labor cost        
 
 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Knowledge Booster
Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,