Determine the correct length of a line 256.32 m long measured using a 50 m steel tape at
30°C. The steel tape was calibrated at 18°C.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- A steel tape is 100.00 ft long and has a weight of 0.0225 lb/ft and is used to measure a line from A to B in two segments (one full tape length and one partial tape length), supported at the ends only for each of the two segments. The recorded distance is 181.83 ft. The pull at the time of measurement is 12 lb. What is the length of the line corrected for sag? (Assume that no other tape corrections need to be applied.)arrow_forwardA steel tape standardized at 20degree celcius and supported through out under tension of 90N Was found to be 30.377m long. The tape had a cross sectional area of 55mm^2 and a weight of 73g/m. This tape was used supported at the ends only with a constant tension of 78N to measure a line from A to B in nine segments. The data given in the following table were recorded. Apply correction for tape, length,temperature,pull,sag and tape not horizontal to determine the correct length of the line Difference in Elevation Cm) 0-392 Section Meacured Recarded Distance) Tempergrare A-1 15 1- 2 30 15 0.301 2-3 30 16 O.191 3-4 16 0-255 4-5 30 16 0-38 5-6 30 8.636 6-7 0.782 7-6 30 0-825 8-8 25.348 18 0.578 Sum = 265-348 marrow_forwardYou measured 300 ul with a 1000ul pipette; The corrected values were the following : 292 ul, 294ul, 287ul, 290ul, 288ul and 293 ul (mean- 290.7 ul and Std. dev + 280 ul) 3. Acceptable values are: Accuracy : 1.0% Precision: 0.5 % Were you accurate? Were you precise? and why? show cakulationsarrow_forward
Recommended textbooks for you
- Structural Analysis (10th Edition)Civil EngineeringISBN:9780134610672Author:Russell C. HibbelerPublisher:PEARSONPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Structural AnalysisCivil EngineeringISBN:9780073398006Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel LanningPublisher:McGraw-Hill EducationTraffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning