Describe the five phases of Preconstruction operations?
- The Preconstruction operations are planning operations which are done before commencement of any construction project.
- The five phases of preconstruction operations are :
1- Client and contractor interaction phase
- The client provide the vision of the project to the contractor after which the contractor gather all the information and planning required for the project.
- The initial budget and project completion time are discussed.
2- Defining objective of the construction operation phase
- Checking the feasibility of construction project.
- Provide plans, ideas and architectural design for construction operations.
- Clients queries are solved by contractor in this phase.
Step by stepSolved in 2 steps
- Q5) What are "kink-band" failure modes?arrow_forwardAre THE Prelitigation records of considerable value during the preparation of the trial outline?arrow_forwardSeismic method of a site investigation is a type of: Sonic drilling Electromagnetic Investigation Non- Intrusive Investigation All of the abovearrow_forward
- Structural Analysis (10th Edition)Civil EngineeringISBN:9780134610672Author:Russell C. HibbelerPublisher:PEARSONPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Structural AnalysisCivil EngineeringISBN:9780073398006Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel LanningPublisher:McGraw-Hill EducationTraffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning