Question

i need solution for part d and part e

1. The demand for subassembly S is 100 units in week
7.Each unit of S requires 1 unit of T and 2 units of U.
Each unit of T requires 1 unit of V, 2 units of W, and 1
unit of X. Finally, each unit of U requires 2 units of Y
and 3 units of Z. One firm manufactures all items. It
takes 2 weeks to make S, 1 week to make T,2 weeks
to make U, 2 weeks to make V, 3 weeks to make W,1
week to make X, 2 weeks to make Y, and 1 week to
make Z.
a) Construct a product structure. Identify all levels,
parents, and
Components.
b) Prepare a time-phased product structure.
c) Construct a gross material requirements plan.
d) In addition to 100 units of S, there is also a demand for
20 units of U, which is a component of S. The 20 units of
U are needed for maintenance purposes. These units are
needed in week 6. Modify the gross material requirements
plan to reflect this change.
e) In addition to 100 units of S, there is also a demandfor
20 units of U, which is a component of S. The 20 units of
U are neededfor maintenance purposes. These units are
needed in week 6. Modify the net material requirements
plan to reflect this change.
expand button
Transcribed Image Text:1. The demand for subassembly S is 100 units in week 7.Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T,2 weeks to make U, 2 weeks to make V, 3 weeks to make W,1 week to make X, 2 weeks to make Y, and 1 week to make Z. a) Construct a product structure. Identify all levels, parents, and Components. b) Prepare a time-phased product structure. c) Construct a gross material requirements plan. d) In addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change. e) In addition to 100 units of S, there is also a demandfor 20 units of U, which is a component of S. The 20 units of U are neededfor maintenance purposes. These units are needed in week 6. Modify the net material requirements plan to reflect this change.
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.