Construct a PERT network from the following table. Find the critical path and variance for each event, if to, tp, and to represent most optimistic, most pessimistic, and most likely times respectively. Activity 1-2 1-3 2-4 2-5 3-4 to tp tm 1 431 193 3 713 1537 275 7 3-6 4-5 4-6 5-7 922 223 663 6 6 123 6-7 7 6 2

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter14: Computational Engineering Tools Electronic Spreadsheets
Section: Chapter Questions
Problem 28P
icon
Related questions
Question

please solve it step by step

Construct a PERT network from the following table. Find the critical path and variance for eachevent, if ??, ??, ??? ?? represent most optimistic, most pessimistic, and most likely timesrespectively

Construct a PERT network from the following table. Find the critical path and variance for each
event, if to, tp, and to represent most optimistic, most pessimistic, and most likely times
respectively.
Activity 1-2 1-3 2-4 2-5 3-4
4
1
5
3
9
3
1
3
7
to
tp
tm
7
1
3
2
7
5
3-6 4-5 4-6 5-7
9
2
6
1
2
2
6
2
2
3
3
3
6-7
7
6
2
Transcribed Image Text:Construct a PERT network from the following table. Find the critical path and variance for each event, if to, tp, and to represent most optimistic, most pessimistic, and most likely times respectively. Activity 1-2 1-3 2-4 2-5 3-4 4 1 5 3 9 3 1 3 7 to tp tm 7 1 3 2 7 5 3-6 4-5 4-6 5-7 9 2 6 1 2 2 6 2 2 3 3 3 6-7 7 6 2
Expert Solution
steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
Mapping
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning