Consider the tabulated design intersection data and based on Webster method, then the number of queued (stopped) vehicles during the red interval for Phase Sis about vehicles. Assuming that Qs is 2200 vphpl. Qa (vph) Yellow All-red ts (sec) Lane 1 Lane 2 Lane 3 (sec) (sec) Phase N 500 600 450 3 Phase S 650 550 500 2 2 Phase EW 300 250 275 2. O a. 12 O b. 15 Oc 22 Od. 18

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter8: Intersection Control
Section: Chapter Questions
Problem 26P
icon
Related questions
Question

Subject : Transportation Engineering

Give me right answer 

Consider the tabulated design intersection data and based on Webster method, then the number of queued (stopped) vehicles during the red interval for Phase S is about
vehicles. Assuming that Qs is 2200 vphpl.
Qa (vph)
All-red
(sec)
Yellow
ts (sec)
Lane 1
Lane 2
Lane 3
(sec)
Phase N
500
600
450
2.
3
Phase S
650
550
500
2
Phase EW
300
250
275
O a. 12
O b. 15
O. 22
Od. 18
Transcribed Image Text:Consider the tabulated design intersection data and based on Webster method, then the number of queued (stopped) vehicles during the red interval for Phase S is about vehicles. Assuming that Qs is 2200 vphpl. Qa (vph) All-red (sec) Yellow ts (sec) Lane 1 Lane 2 Lane 3 (sec) Phase N 500 600 450 2. 3 Phase S 650 550 500 2 Phase EW 300 250 275 O a. 12 O b. 15 O. 22 Od. 18
Expert Solution
steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Knowledge Booster
The profession of transportation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning