
Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
thumb_up100%
Consider the network described in the table below.
Activity |
Immediate Predecessor(s) |
Pessimistic |
Probable |
Optimistic |
J |
-- |
15 |
10 |
8 |
K |
-- |
9 |
8 |
7 |
L |
J |
10 |
6 |
5 |
M |
J |
3 |
3 |
3 |
N |
K, M |
9 |
5 |
1 |
O |
K, M |
10 |
7 |
4 |
P |
L, N |
10 |
8 |
3 |
Draw the network diagram and answer the following questions.
(a) Calculate the expected duration of each activity.
(b) Calculate the expected duration and variance of the critical path.
(c) Calculate the probability that the project will be completed in more than 28-time units.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 5 steps with 1 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Identify the critical path(s)arrow_forwardConsider the office renovation project data in Table 7.16. A“zero” time estimate means that the activity could take a verysmall amount of time and should be treated as a numericzero in the analysis.a. Based on the critical path, find the probability ofcompleting the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure ofcompleting the project.arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre-decessors, and times appear in the accompanying table: A—2 B—5 C—1 D B 10 E A, D 3 FC6 G E, F 8 A) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time? Please answer A B C and show workarrow_forward
- Given the information below, what are the estimated expected (mean) times (in weeks) for activities A-H? What are the estimated standard deviations (in weeks) in the times for activities A-H?arrow_forwarddraw the network diagramarrow_forwardActivity Preceded By ABCDEFG А ww ww A B,C D E BC F. G Expected Time Regular Crash 6 days 2 day 12 6 4 10 8 C 18 6 2 6 6 2 8 4 Direct Cost Regular Crash $2000 $3800 2000 10000 4000 4600 3900 5000 7600 16000 19600 2000 4000 1000 3400 2800 Requested: (a) Construct a network including the Early and Late Start and Finish times. (b) Identify the normal Critical Path(s) and the normal expected completion time (c) Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?arrow_forward
- QUESTION 8 Consider the activities, durations, and predecessor relationships in the following network, shown in Table 6 below. Draw the network and answer the questions that follow. Table 5 Pessimistic Activity Description Most Likely (Weeks) Immediate Optimistic Predecessor(s) (Weeks) (Weeks) A 4 10 --- A 2 8 20 A 12 16 D 1 2 E D, C 22 F 3 4 G F 2 2 F 6 8 10 E, G, H 4 8 12 J 2 3 a) What is the expected time for activity B? b) What is the variance for activity B? c) Based on the calculation of estimated times, what is the critical path? d) What is the estimated time of the critical path? e) What is the activity variance along the critical path? f) What is the probability of completion of the project before week 42?arrow_forward2.1: For each of the following projects, determine the shape of its life cycle (S or J): SOLUTION (Answer just near the name of the project) • Building a nuclear station for electrical power generation– • Achieving an ILETS minimum score – • Organizing a wedding party – • Getting a masters degree in engineering management –arrow_forwardThe manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Activity Optimistic Most Probable Pessimistic Immediate Predecessors A 1 2 3 - B 4 6 8 A C 2 4 6 A D 1 2 3 B, C E 2 3 4 B F 1 2 3 A G 1 2 3 D H 1 2 3 G I 1 1 1 E, H, F A. Draw a project network for this problem. B. Fill in all the blanks in the following table. Note: For variance (σ2) in activity time, keep two decimal places. Activity Expected Time t (weeks) Variance σ2 ES EF LS LF Slack Critical Path? A B C D…arrow_forward
- Network Analysis Given this WBS, draw out a network diagram and use the two-pass and enumera methods to answer the following questions. Activity LCT 50 - b a-d-g-j Predecessor Ob-f-i Oa-c-f-i a-e-h-j a a a b, c d d, e f g, h <*** Duration 5 days Saved 434 994 6 4 5 Question 6 (1 point) Consider the network above. What is the critical path for this project? 6 6arrow_forwardDevelop a project network. Determine the expected project completion time. What is the probability that the project completion time will be completed? With in 2 weeks earlier than the expected project completion time? With in 1.5 week more than the expected project completion time ?arrow_forwardCase Study The South-to-North Water Diversion Project in China is the largest of its kind ever undertaken. The project involves drawing water from southern rivers and supplying it to the dry north. This massive scheme has already taken 50 years from conception to commencement and is expected to take almost as long to construct. Planned for completion in 2050, it will eventually divert 44.8 billion cubic metres of water annually to the population centres of the drier north. When finished, the work will link China's four main rivers - the Yangtze, Yellow River, Huaihe and Haihe - and requires the construction of three diversion routes, stretching south-to-north across the eastern, central and western parts of the country. The complete project is expected to cost $62bn - more than twice as much as the country's controversial Three Gorges Dam.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.