Chairs Tables
Selling price per unit $80 $400
Variable cost per unit $30 $200
Board feet per unit 2 10
Monthly demand 600 100
The company's supplier of hardwood will only be able to supply 2,000 board feet this month.
What plan would maximize profits?
a. 500 chairs and 100 tables
b. 600 chairs and 80 tables
c. 500 chairs and 80 tables
d. 600 chairs and 100 tables
Note:-
- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
- Answer completely.
- You will get up vote for sure.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps
Knowledge Booster
Similar questions
- If 10 pallets are received each 8-hour day, what is the average number of pallets in the system on any given day? Stocking 9 persons 1. 5 hpp S/R Cycle Count person 0.5 hrs/pallet (hpp) Pricing 2 persons 1.25 hpp 1 person 0.25 hpp Spotting 1 persons 0.2 hpp O 10 pallets O 4.713 pallets O 4.375 pallets O125 pallets O Impossible to determinearrow_forwardLast Year Sales $208,000 $221,000 Cost of goods sold 106,000 116,000 Gross margin 102,000 105,000 Other expenses 49,000 49,000 Net income 53,000 56,000 Finished goods inventory 2,700 5,000 Work-in-process inventory 11,000 8,000 Raw material inventory 5,500 7,000 Total inventory (average for year) 19,200 20,000 Other current assets 93,000 109,000 Other assets 210,000 249,000 Total assets 322,200 378,000 ^THIS YEAR The plant manager, Murat Kristal, at York Technologies makes Aircraft Navigation Systems. He expects you, as the new OM analyst, to provide some insight for performance of the plant. High on his list is an understanding of his inventory…arrow_forwardAssistance for question 5 pleasearrow_forward
- 12.4 A company has a warehouse with the dimensions shown in the following diagram. How many pallets measuring 48"x40" can be stored three high if there is to be a 2" space between the pallets? 50' Aisle Aisle 4' 4' 4' R 4'arrow_forwardThe 10th annual bowling tournament is at your hotel in June. The group has a lot of audio-visual (AV) needs that the hotel will need to provide. The hotel has some basic AV equipment but does not have some of the items on the client’s request list. Which of the following strategies should the hotel employ so that the hotel and the client both benefit in this situation? Question 17 options: a) Rent the equipment and for convenience blend the cost into the budget for the client. b) Offer the client flip charts and markers instead of a projector for a lower price. c) Do not meet the guest’s needs and offer him a complimentary guest room for his trouble. d) Send the guest to the hotel next door for the AV portion of their meeting.arrow_forwardEach Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 4,500 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 8,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 3,500 Week 1 2 3 Gross requirements 4,500 1,000…arrow_forward
- 1. Describe the risks associated with the system depicted in the flowchart below. 2. Describe the physical controls needed to mitigate each risks. Purchases Department Receiving Department Čentral Computer Facility Account Payable Department Warehouse Packing Slip A Vendor PO Invoice Rec Reprt Identify Items Prepare Receiving report Accaunting System and Select Vendar Recomcile Reconcile and documents and Update Packing Slip Rec Reprt set up Liability Inventory Tmventory Records PO Rec Reprt Rec Reprt PO Invoice ACLOunt PO Paryable Rec Reprt Vendorarrow_forwardNeed d and earrow_forwardWhen evaluating sales revenue which critical factor(s) must be considered? a) Number of operating meal periods or days b) Changes in menu prices, guest counts, and check averages c) Special events d) All of the abovearrow_forward
- Q7.An example of a leading performance measure is: a. Number of new customers b. Production cycle timearrow_forwardComplete a fish-bone chart explaining how a pizza delivery can arrive late on a Friday or Saturday. Match each number in the chart with corresponding reason. I Manpower Not enough training Ingredient shortage Not enough boxes Drivers get lost Material Low pay/ high turnover II Source of error 11 III IV III Methods Turnover Training not sufficient Machinery Can't handle large orders Credit card machine broken Too few phones Reason Oven breaks ▼ IV ▼ ▼ Late weekend pizza deliveryarrow_forward10arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.