CAPITAL BUDGETING CRITERIA You must analyze two projects, X and Y. Each project costs $10,000, and the firm's WACC is 12%. The expected net cash flows are as follows: 1 4 + Project X - $10,000 Project Y -$10,000 $6,500 $3,500 $3,000 $3,500 $3,000 $3,500 $1,000 $3,500 a. Calculate each project's NPV, IRR, MIRR, payback, and discounted payback. b. Which project(s) should be accepted if they are independent? c. Which project(s) should be accepted if they are mutually exclusive? d. How might a change in the WACC produce a conflict between the NPV and IRR rankings of the two projects? Would there be a conflict if WACC were 5%? (Hint: Plot the NPV profiles. The crossover rate is 6.21875%.) e. Why does the conflict exist?

Intermediate Financial Management (MindTap Course List)
13th Edition
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Eugene F. Brigham, Phillip R. Daves
Chapter12: Capital Budgeting: Decision Criteria
Section: Chapter Questions
Problem 10P: Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year...
icon
Related questions
Question
CAPITAL BUDGETING CRITERIA You must analyze two projects, X and Y. Each
project costs $10,000, and the firm's WACC is 12%. The expected net cash flows are
as follows:
1
4
+
Project X - $10,000
Project Y -$10,000
$6,500
$3,500
$3,000
$3,500
$3,000
$3,500
$1,000
$3,500
a. Calculate each project's NPV, IRR, MIRR, payback, and discounted payback.
b. Which project(s) should be accepted if they are independent?
c. Which project(s) should be accepted if they are mutually exclusive?
d. How might a change in the WACC produce a conflict between the NPV and IRR
rankings of the two projects? Would there be a conflict if WACC were 5%? (Hint: Plot
the NPV profiles. The crossover rate is 6.21875%.)
e. Why does the conflict exist?
Transcribed Image Text:CAPITAL BUDGETING CRITERIA You must analyze two projects, X and Y. Each project costs $10,000, and the firm's WACC is 12%. The expected net cash flows are as follows: 1 4 + Project X - $10,000 Project Y -$10,000 $6,500 $3,500 $3,000 $3,500 $3,000 $3,500 $1,000 $3,500 a. Calculate each project's NPV, IRR, MIRR, payback, and discounted payback. b. Which project(s) should be accepted if they are independent? c. Which project(s) should be accepted if they are mutually exclusive? d. How might a change in the WACC produce a conflict between the NPV and IRR rankings of the two projects? Would there be a conflict if WACC were 5%? (Hint: Plot the NPV profiles. The crossover rate is 6.21875%.) e. Why does the conflict exist?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT