Question
Calculate
- BAC=$20,000
- EV=$19,000
- PV=$19,000
- AC=$17,000
CPI=Answer
TCPI=Answer
How reasonable is the prediction that we will finish the project on budget? Given our performance so far:
We are being too optimistic thinking that we will complete the project on budget - we will probably finish the project over budget
It is a reasonable assumption to think that we will complete the project on budget
We are being too conservative - we will come in well under budget at this rate
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 4 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.Similar questions
- Make sure all parts to be solved...arrow_forwardWhich of the following is false? If an activity has a slack value greater than zero, it needs to be a critical activity O Lateness in activities, which are not located on the critical path, may or may not result in lateness in overall project completion time, depending on their slack time If there is only one activity in a project, it needs to be a critical activity O If Activity A needs to be completed before Activity B starts, Activity A is the immediate predecessor of activity B O Lateness in any of the activities located on the critical path would result in lateness in overall proiect completion timoarrow_forwardWhat cost would an accounting statement reveal should current decisions be based on accounting cost.arrow_forward
- An average variable cost function is estimated as AVC = 96-2Q + 0.05Q2. Which of the following cost functions is associated with this estimate? a. MC = -2Q + 0.1Q2 b. TVC = 96Q-2Q2 + 0.1Q3 c. TVC = 96Q - 4Q2 +0.15Q3 d. MC 96-4Q+0.15Q2 =arrow_forwardUsing Techniques Units of Variable Inputs Produce K 1 unit of output A 8 B 4 12 2 units of output A 14 12 B 20 3 units of output A 16 12 B 12 22 1) Assume that the relevant time period is the short run. Assuming the price of labor (L) is RM5 per unit and the price of capital (K) is RM10 per unit, the average variable cost of producing two units of output is, -(1M) Working calculation: 20 Assume the price of labor (4) is RM5 per unit, the price of capital (K) is RM10 per unit, and that firms attempt to minimize costs. The marginal cost of producing the third unit of output is - (1M) Working calculation:arrow_forwardA firm has the following total revenue and total cost schedules: TR = $3Q. TC = $4,000 + $1.7Q. What is the break-even level of output? Round your answer to the nearest whole number. units What is the level of profits at sales of 4,500 units? Round your answer to the nearest dollar. $ As the result of a major technological breakthrough, the total cost schedule is changed to: TC = $6,500 + $0.5Q. What is the break-even level of output? Round your answer to the nearest whole number. units What is the level of profits at sales of 4,500 units? Round your answer to the nearest dollar. $arrow_forward
- ECONOMICS UPVOTE WILL BE GIVEN. PLEASE CHOOSE THE CORRECT ANSWER. NO LONG EXPLANATION NEEDED. A manufacturer produces and sells exactly 600,000 units of a single product annually. The fixed cost of the company is Php 180 million per year, and the variable cost is Php 2,350 per unit. In the coming year, the company is selling its product at a price of Php 2,800 per unit. How much is the total variable cost? A. Php 2,350 B. Php 1,680,000,000 C. Php 1,410,000,000 D. Php 180,000,000arrow_forwardTable COST11: Monthly Costs, Revenues and Other Information for a Bakery Product Price (P*) = $8 %3D Items Sold (Q*) = %3D 1,500 Health and Safety Inspection Costs = $140 Spouse's Former Wages (as the Owner's Assistant) = $1,500 %3D %3D The Entrepreneur's Former Earning = $1,600 %3D Home Delivery Expenses = $400 Production Materials Costs $2,450 Wages Paid to Workers (wL) = $2,050 Rent & Utility Payments = $1,500 According to information in Table Cost11 for a competitive firm, accounting and economic profits are and respectively. $5,260; $2,160 O $5,260; $2,060arrow_forwardThe total cost (CT) of Holdins-up is CT = 4q2 + 4q + 16CT = 4q2 + 4q + 16. Get the fixed cost (CF) and the variable cost (CV) of the company. CF=4q^2+4; CV=16 CF=16;CV=4q^2+4q CF=0;CV=4q^2+4q+16 CF=4q^2+4q; CV=0arrow_forward
- In a Project Cost- Duration Graph, total project costs are a sum of Labor, material and equipment costs Direct and indirect costs Direct costs plus interest Direct costs and the project manager's salaryarrow_forwardkk.2arrow_forwardRiver Girl Fly Fishing Shop applies overhead at a rate of $5 per direct labor hour. At the end of the month, the company had accumulated 7000 direct labor hours and incurred $38000 in manufacturing overhead. Manufacturing overhead was $600 underapplied. $3000 underapplied. $600 overapplied. $3000 overapplied.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education