b. What is the critical path? A-C-F-H A-D-G-H OB-E-G-H A-D-F-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. Project completion time days

A First Course in Probability (10th Edition)
10th Edition
ISBN:9780134753119
Author:Sheldon Ross
Publisher:Sheldon Ross
Chapter1: Combinatorial Analysis
Section: Chapter Questions
Problem 1.1P: a. How many different 7-place license plates are possible if the first 2 places are for letters and...
icon
Related questions
Question

also part D -- "what is the probability of completing the project within 23 days?"

b. What is the critical path?
O A-C-F-H
A-D-G-H
B-E-G-H
O A-D-F-H
c. What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
Project completion time
days
Transcribed Image Text:b. What is the critical path? O A-C-F-H A-D-G-H B-E-G-H O A-D-F-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. Project completion time days
The following represents a project that should be scheduled using CPM:
TIMES (DAYS)
IMMEDIATE
ACTIVITY PREDECESSORS
A BUDAFCE
A
В
с
G
H
AADUDE
А
А
B
C,D
D,E
F,G
a
L1233
E466NNSN6
m
2
2
5
2
b
7
11
。669 wyl
7
13
Transcribed Image Text:The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE ACTIVITY PREDECESSORS A BUDAFCE A В с G H AADUDE А А B C,D D,E F,G a L1233 E466NNSN6 m 2 2 5 2 b 7 11 。669 wyl 7 13
Expert Solution
steps

Step by step

Solved in 3 steps with 21 images

Blurred answer
Similar questions
Recommended textbooks for you
A First Course in Probability (10th Edition)
A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON
A First Course in Probability
A First Course in Probability
Probability
ISBN:
9780321794772
Author:
Sheldon Ross
Publisher:
PEARSON