Consider the following data set for an office structure built by Anderson Construction Co. The completed building is nine stories. However, construction was interrupted by a fire after 5.3357 floors were completed. At the time of the fire, Anderson had used 54,067 hours of labor to construct the first 5.3357 stories of the building. It then took Anderson an additional 40,750 labor hours to complete this nine-story building. In this problem, FLRCOM is the number of floors completed, and HOURS is cumulative labor hours to complete the number of floors given by FLRCOM. Enter the data for FLRCOM and HOURS in Minitab and use one command to create a variable which is the square of FLRCOM. Call this new variable FLRCOMSQ. Estimate the function: HOURS = a + b(FLRCOM) + c(FLRCOMSQ). Graph this equation. Assume that the fire caused construction to slow down and caused a reduction in efficiency in completing the building. Estimate the number of labor hours needed to complete the building if there were no slow down related to the fire. Assume that the relationship that existed between HOURS and FLRCOM and FLRCOMSQ before the fire would have continued to exist to the completion of the building had the fire not occurred. Estimate the extra labor hours traceable to the fire.   Row HOURS FLRCOM 1 800 0.0431 2 1575 0.0864 3 2708 0.1564 4 4110 0.2498 5 5721 0.3676 6 7955 0.5319 7 8012 0.5362 8 10765 0.7508 9 13757 1.0098 10 17257 1.3273 11 21121 1.6684 12 22435 1.8007 13 26194 2.1873 14 29971 2.5881 15 30266 2.6262 16 34296 3.0633 17 37027 3.3722 18 41556 3.8899

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
  1. Consider the following data set for an office structure built by Anderson Construction Co. The completed building is nine stories. However, construction was interrupted by a fire after 5.3357 floors were completed. At the time of the fire, Anderson had used 54,067 hours of labor to construct the first 5.3357 stories of the building. It then took Anderson an additional 40,750 labor hours to complete this nine-story building.

In this problem, FLRCOM is the number of floors completed, and HOURS is cumulative labor hours to complete the number of floors given by FLRCOM.

Enter the data for FLRCOM and HOURS in Minitab and use one command to create a variable which is the square of FLRCOM. Call this new variable FLRCOMSQ.

  1. Estimate the function:

HOURS = a + b(FLRCOM) + c(FLRCOMSQ).

  1. Graph this equation.
  2. Assume that the fire caused construction to slow down and caused a reduction in efficiency in completing the building. Estimate the number of labor hours needed to complete the building if there were no slow down related to the fire. Assume that the relationship that existed between HOURS and FLRCOM and FLRCOMSQ before the fire would have continued to exist to the completion of the building had the fire not occurred.
  3. Estimate the extra labor hours traceable to the fire.

 

Row

HOURS

FLRCOM

1

800

0.0431

2

1575

0.0864

3

2708

0.1564

4

4110

0.2498

5

5721

0.3676

6

7955

0.5319

7

8012

0.5362

8

10765

0.7508

9

13757

1.0098

10

17257

1.3273

11

21121

1.6684

12

22435

1.8007

13

26194

2.1873

14

29971

2.5881

15

30266

2.6262

16

34296

3.0633

17

37027

3.3722

18

41556

3.8899

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question
  1. Assume that the fire caused construction to slow down and caused a reduction in efficiency in completing the building. Estimate the number of labor hours needed to complete the building if there were no slow down related to the fire. Assume that the relationship that existed between HOURS and FLRCOM and FLRCOMSQ before the fire would have continued to exist to the completion of the building had the fire not occurred.
  2. Estimate the extra labor hours traceable to the fire.

 

Solution
Bartleby Expert
SEE SOLUTION
Knowledge Booster
Integers
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman