As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. Click the icon to view the product structure. Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (2 weeks), casting (4 weeks), bearing (1 week), and shaft (1 week). a) Choose the correct time-phased product structure for the bracket. O A. В. D. handle handle handle handle clamp clamp clamp clamp casting base casting base casting base casting base bearing bearing bearing bearing bracket bracket bracket bracket housing housing housing housing shaft spring shaft spring shaft spring shaft spring handle handle handle handle clamp clamp clamp clamp casting casting casting casting 4 6. 7 8 9 10 3. 4 5 6 7 8 9 10 3 4 5 6 7 8 9 10 3 4 7 89 10 Time in weeks Time in weeks Time in weeks Time in weeks b) In what week do you need to start the castings?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

2)The castings need to be started in week ? (enter your response as a whole number​).

As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The
base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand.
Click the icon to view the product structure.
Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times
for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (2 weeks), casting (4 weeks), bearing (1 week),
and shaft (1 week).
a) Choose the correct time-phased product structure for the bracket.
O A.
В.
D.
handle
handle
handle
handle
clamp
clamp
clamp
clamp
casting
base
casting
base
casting
base
casting
base
bearing
bearing
bearing
bearing
bracket
bracket
bracket
bracket
housing
housing
housing
housing
shaft
spring
shaft
spring
shaft
spring
shaft
spring
handle
handle
handle
handle
clamp
clamp
clamp
clamp
casting
casting
casting
casting
4
6.
7
8 9 10
3.
4
5 6 7 8
9 10
3 4
5 6
7
8
9 10
3
4
7 89 10
Time in weeks
Time in weeks
Time in weeks
Time in weeks
b) In what week do you need to start the castings?
Transcribed Image Text:As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. Click the icon to view the product structure. Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (2 weeks), casting (4 weeks), bearing (1 week), and shaft (1 week). a) Choose the correct time-phased product structure for the bracket. O A. В. D. handle handle handle handle clamp clamp clamp clamp casting base casting base casting base casting base bearing bearing bearing bearing bracket bracket bracket bracket housing housing housing housing shaft spring shaft spring shaft spring shaft spring handle handle handle handle clamp clamp clamp clamp casting casting casting casting 4 6. 7 8 9 10 3. 4 5 6 7 8 9 10 3 4 5 6 7 8 9 10 3 4 7 89 10 Time in weeks Time in weeks Time in weeks Time in weeks b) In what week do you need to start the castings?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.