An intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired. O 15.552 sec Phase Allowed movements Analysis flow rate Saturation flow rate O 11.462 sec NBL, SBL 330, 365 dlh 1700, 1750 vvh NBT/R, SBT/R 1125, 1075 vhh 3400, 3300 veh Using v/c equalization ratio, calculate the effective green time for phase 3 EBL, WBL 110, 80 velvh 650, 600 vehh EBTR, WBTR 250, 285 velh 1750, 1800 velv

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter8: Intersection Control
Section: Chapter Questions
Problem 8P
icon
Related questions
Question
An intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis
and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical
intersection v/c of 0.90 is desired.
O 15.552 sec
O 11.462 sec
O 14.825 sec
Phase
O 16.065 sec
Allowed movements
Analysis flow rate
Saturation flow rate
Using v/c equalization ratio, calculate the effective green time for phase 3
1
NB L, SB L
330, 365 veh/h
1700, 1750 veh/h
2
NB T/R, SB T/R
1125, 1075 veh/h
3400, 3300 veh/h
EB L, WB L
110, 80 veh/h
650, 600 veh/h
3
EB T/R, WB T/R
250, 285 veh/h
1750, 1800 veh/h
Transcribed Image Text:An intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired. O 15.552 sec O 11.462 sec O 14.825 sec Phase O 16.065 sec Allowed movements Analysis flow rate Saturation flow rate Using v/c equalization ratio, calculate the effective green time for phase 3 1 NB L, SB L 330, 365 veh/h 1700, 1750 veh/h 2 NB T/R, SB T/R 1125, 1075 veh/h 3400, 3300 veh/h EB L, WB L 110, 80 veh/h 650, 600 veh/h 3 EB T/R, WB T/R 250, 285 veh/h 1750, 1800 veh/h
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Intersection design
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning