An electric switch manufacturing company is trying to decide between three different assembly methods. Method A has an estimated first cost of $46,000, an annual operating cost (AOC) of $7,000, and a service life of 2 years. Method B will cost $86,000 to buy and will have an AOC of $3,500 over its 4-year service life. Method C costs $115,000 initially with an AOC of $6,000 over its 8-year life. Methods A and B will have no salvage value, but Method C will have equipment worth 12% of its first cost. Perform a future worth analysis to select the method at /= 10% per year. The future worth of method A is $ The future worth of method B is $ The future worth of method C is $ Method: (Click to select) is selected. (Click to select C CBA A

Essentials of Business Analytics (MindTap Course List)
2nd Edition
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Chapter15: Decision Analysis
Section: Chapter Questions
Problem 5P: Hudson Corporation is considering three options for managing its data warehouse: continuing with its...
icon
Related questions
Question
An electric switch manufacturing company is trying to
decide between three different assembly methods. Method
A has an estimated first cost of $46,000, an annual
operating cost (AOC) of $7,000, and a service life of 2 years.
Method B will cost $86,000 to buy and will have an AOC of
$3,500 over its 4-year service life. Method C costs $115,000
initially with an AOC of $6,000 over its 8-year life. Methods
A and B will have no salvage value, but Method C will have
equipment worth 12% of its first cost.
Perform a future worth analysis to select the method at /= 10% per year.
The future worth of method A is $
The future worth of method B is $
The future worth of method C is $
Method: (Click to select) is selected.
(Click to select
C
CBA
A
Transcribed Image Text:An electric switch manufacturing company is trying to decide between three different assembly methods. Method A has an estimated first cost of $46,000, an annual operating cost (AOC) of $7,000, and a service life of 2 years. Method B will cost $86,000 to buy and will have an AOC of $3,500 over its 4-year service life. Method C costs $115,000 initially with an AOC of $6,000 over its 8-year life. Methods A and B will have no salvage value, but Method C will have equipment worth 12% of its first cost. Perform a future worth analysis to select the method at /= 10% per year. The future worth of method A is $ The future worth of method B is $ The future worth of method C is $ Method: (Click to select) is selected. (Click to select C CBA A
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 1 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials of Business Analytics (MindTap Course …
Essentials of Business Analytics (MindTap Course …
Statistics
ISBN:
9781305627734
Author:
Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning