A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two alternatives, A and B, have been identified, and the associated costs and revenues have been estimated. Annual fixed costs would be $39,000 for A and $21,000 for B; variable costs per unit would be $10 for A and $11 for B; and revenue per unit would be $15.
a. Determine each alternative’s break-even point in units. (Round your answer to the nearest whole amount.)
b. At what volume of output would the two alternatives yield the same profit (or loss)? (Round your answer to the nearest whole amount.)
c. If expected annual demand is 16,000 units, which alternative would yield the higher profit (or the lower loss)?
Trending nowThis is a popular solution!
Step by stepSolved in 4 steps
- In an essay, suppose you are opening up an an Applesbee's restaurant. describe the capacity analysis of the process, including the strategies used to adress expected customer demandarrow_forwardWhen many processes are running at the same time, how does the capacity analysis react?arrow_forwardDefine the Process selection and capacity planning influence system design?arrow_forward
- Dr. Gulakowicz is an orthodontist. She estimates that adding two new chairs will increase fixed costs by $ 145 comma 000$145,000, including the annual equivalent cost of the capital investment and the salary of one more technician. Each new patient is expected to bring in $ 3 comma 010$3,010 per year in additional revenue, with variable costs estimated at $ 970$970 per patient. The two new chairs will allow Dr. Gulakowicz to expand her practice by as many as 190190 patients annually. How many patients would have to be added for the new process to break even?arrow_forwardWhen many processes are occurring simultaneously, what type of answer does the capacity analysis get?arrow_forwardAnswer for type Barrow_forward
- Explain what a capacity in chunks mean and why is it a consideration in capacity planning? It's from operations management domain don't sent it otherways !!arrow_forwardJ 1 ue K Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 10 transplants under great scrutiny and at no cost to the patients with the hospital picking the expenses. The cost per hour of surgery is estimated to be $5,000. The very first transplant, just completed, required 27 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: a) the 10th transplant hours (round your response to two decimal places). Learning Curve Coefficients Unit Number (N) 10 Unit Time .385 75% Total Time 5.589 Unit Time .477 80% Total Time 6.315 Unit Time .583 85% Total Time 7.116 Xarrow_forwardCASE 1: If the medical team continues to treat Dax, which of the following capacity assessment criteria are they most likely questioning? Dax's ability to understand the risks and benefits Dax's ability to appreciate the full-force of his decision Dax's ability to give clear reasoning for his decisionarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.