a. Calculate the labor productivity of both Archer Contracting and Bronson Con- struction. Who is the most productive according to this measure? b. Assume that both Archer Contracting and Bronson Construction pay their employees $15 an hour and each employee works 8 hours per day. Calculate the multifactor productivity of each firm. Now who is the most productive and by how much? c. Now assume that both Archer Contracting and Bronson Construction pay their employees $35 an hour and each employee works 8 hours per day. Calculate the multifactor productivity of each firm. Now who is the most productive and by how much?

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question

snip

Archer Contracting repaved 50 miles of two-lane county roadway with a crew of
six employees. This crew worked 8 days and used $7,000 worth of paving mate-
rial. Nearby, Bronson Construction repaved 30 miles of four-lane interstate roadway
working 10 days with a crew of five people using $9,000 of paving material. Both
Archer Contracting and Bronson Construction rented the same paving equipment to
complete their respective assignments, costing each $1,500 a day.
Transcribed Image Text:Archer Contracting repaved 50 miles of two-lane county roadway with a crew of six employees. This crew worked 8 days and used $7,000 worth of paving mate- rial. Nearby, Bronson Construction repaved 30 miles of four-lane interstate roadway working 10 days with a crew of five people using $9,000 of paving material. Both Archer Contracting and Bronson Construction rented the same paving equipment to complete their respective assignments, costing each $1,500 a day.
a. Calculate the labor productivity of both Archer Contracting and Bronson Con-
struction. Who is the most productive according to this measure?
b. Assume that both Archer Contracting and Bronson Construction pay their
employees $15 an hour and each employee works 8 hours per day. Calculate the
multifactor productivity of each firm. Now who is the most productive and by
how much?
c. Now assume that both Archer Contracting and Bronson Construction pay their
employees $35 an hour and each employee works 8 hours per day. Calculate the
multifactor productivity of each firm. Now who is the most productive and by
how much?
Rectangula
d. Why does the conclusion concerning who is the most productive differ when
employees receive $15 an hour (part b) versus $35 an hour (part c)?
Transcribed Image Text:a. Calculate the labor productivity of both Archer Contracting and Bronson Con- struction. Who is the most productive according to this measure? b. Assume that both Archer Contracting and Bronson Construction pay their employees $15 an hour and each employee works 8 hours per day. Calculate the multifactor productivity of each firm. Now who is the most productive and by how much? c. Now assume that both Archer Contracting and Bronson Construction pay their employees $35 an hour and each employee works 8 hours per day. Calculate the multifactor productivity of each firm. Now who is the most productive and by how much? Rectangula d. Why does the conclusion concerning who is the most productive differ when employees receive $15 an hour (part b) versus $35 an hour (part c)?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 12 images

Blurred answer
Knowledge Booster
Economic Efficiency
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education