A surveyor counted 50, 52, 53, 51, 53, and 51 paces in walking along a 45 m course laid out on a concrete pavement. He then took 768, 771, 772, 770, 769, and 770 paces in walking an unknown distance XY. His pace factor should be equal to:
A surveyor counted 50, 52, 53, 51, 53, and 51 paces in walking along a 45 m course laid out on a concrete pavement. He then took 768, 771, 772, 770, 769, and 770 paces in walking an unknown distance XY. His pace factor should be equal to:
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
100%
choices:
a) 0.87 m/pace
b) 1.15 m/pace
c) 0.69 m/pace
d) 1.51 m/pace
pls answer in complete solution.
pls answer in 2 dec places all final answers.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning