A quality control inspector has taken four samples with fi ve
observations each at the Beautiful Shampoo Company, measuring
the volume of shampoo per bottle. If the average range for the four
samples is 0.4 ounces and the average mean of the observations is
19.8 ounces, develop 3-sigma control limits for the bottling operation.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 3 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- What does a run of 5 points above or below the centerline in a control chart imply?arrow_forwardA shirt manufacturer buys cloth by the roll from a supplier. For setting up a control chart to manage the irregularities (e.g., loose threads and tears), the following data were collected from a sample provided by the supplier. Sample Irregularities 1 2 2 1 3 4 4 2 5 0 6 4 7 3 8 0 9 2 10 1 Total 19 Calculate the LCL and UCL for a c-chart with z=2 LCL= 0, UCL = 4.66 LCL= 0, UCL = 3.28 LCL= -0.86, UCL = 3.28 LCL= -0.86, UCL = 3.51 LCL= -0.86, UCL = 4.66arrow_forwardDistinguish between a sampling error and a nonsampling error.How can each be reduced?arrow_forward
- A microbrewery tracks its output in gallons over a five hour period for each of seven days. Their data is in the table below, and they went ahead and calculated the averages and ranges for the individual samples and the overall averages Their data and the factors tables can be found below. Calculate the upper (LCL) and lower (UCL) control limits for X bar, and R charts for their process. Day (X values) X̅ R 1 46 49 45 47 48 47.0 4 2 43 52 46 52 44 47.4 9 3 45 55 46 51 43 48.0 12 4 39 44 42 43 40 41.6 5 5 45 50 48 50 42 47.0 8 6 44 48 45 45 40 44.4 8 7 41 44 52 50 47 46.8 11 X̿ = 46.03 R̅ 8.14 Xbar chart - LCL = 40.48, UCL=46.25, R chart LCL=0, UCL=14.01 Xbar chart - LCL = 44.21, UCL=48.41, R chart LCL=0.49, UCL=17.18 Xbar chart - LCL = 42.61, UCL=49.45, R chart LCL=0.65, UCL=15.63 Xbar chart - LCL = 44.21, UCL=51.62, R chart LCL=0, UCL=17.18 Xbar chart - LCL = 41.31, UCL=50.75, R chart LCL=0, UCL=17.18arrow_forwardCartons of Plaster are supposed to weigh exactly 32 ounces. Inspectors want to develop process control charts. They take five samples of six (6) boxes each and weigh them. Sample means (X-bar) are: 33.8, 34.6, 34.7, 34.1, and 34.2 respectively. Also, the corresponding ranges are: 1.1,0.3, 0.4. 0.7, and 0.3, respectively. The lower and upper control limits of the xbar-chart are respectively O a. None is correct O b. 30.11 and 40.15 O c. 34.01 and 34.55 O d. 33.12 and 34.12 O e. 37.01 and 39.23arrow_forwardCan you please explain the steps to create the control chart ?arrow_forward
- Hermitage DNA Labs, LLC collected temperature readings in an analysis process. The data can be found in the Problems Data Compute the mean and range of each sample and calculate control limits for x-bar and R charts using the appropriate From the charts constructed, does the process appear to be in statistical control?arrow_forwardDESIGNING A CONTROL CHART EXAMPLE Fujiyama Electronics, Inc. has been having difficulties with circuit boards purchased from an outside supplier. Unacceptable variability occurs between two drilled holes that are supposed to be 5 cm apart on the circuit boards. Thirty samples of 4 boards each were taken from shipments from the supplier as shown in the data listed below. Construct x and R charts for the process using the following data. DATA Sample No Samples 1 4.92 4.26 4.94 4.29 2 4.65 5.54 5.00 5.42 3 5.77 5.26 4.76 4.79 4 6.25 4.88 5.66 4.44 5 5.27 5.41 6.02 4.91 6 5.22 5.38 5.08 4.65 7 5.47 4.68 4.56 4.70 8 5.71 4.54 4.17 4.87 9 5.24 5.58 4.72 5.41 10 4.42 5.18 4.79 4.73 11 5.14 4.26 4.71 5.48 12 4.92 5.78 5.50 5.05 13 5.79 3.83 4.30 4.78 14 4.92 4.80 4.75 5.59 15 5.68…arrow_forwardExplain Which type of quality control would be most suitable for the manufacturing of canned beverages? Process control or acceptance sampling?arrow_forward
- concernedas to whether caulking tubes are being properly capped. Ifa significant proportion of the tubes are not being sealed,Webster is placing its customers in a messy situation.Tubes are packaged in large boxes of 144. Several boxes areinspected, and the following numbers of leaking tubes arefound: Calculate p-chart three-sigma control limits to assesswhether the capping process is in statistical control.arrow_forwardJus de Fruit Co. has set up for automated production of its new bottled Triple Berry Colada. Six samples were taken during the first week of production. The OM team wants to check if the dispersion of the process is in control. What will be the 3-sigma upper and lower control limits, respectively? Sample Bottle 1 Bottle 2 Bottle 3 Bottle 4 1 16.5 16.3 15.7 16.2 2 16.1 16 15.5 16.1 3 16.3 16.5 15.8 15.7 4 15.6 16 16.3 16.2 5 16 15.9 16.2 15.8 6 15.9 16.3 16.1 15.5arrow_forwardPlease answer this question What is the acceptable standard deviation range for running of quality controls?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.