A fence 18 feet by 18 feet is being built for $72,000.00 in 4 weeks. During week 2, 30’ feet has been completed and & $36,000.00 has been spent. Calculate the following: •   Estimate to Completion (ETC) • Variance at Completion (VAC) • To Complete Performance Index (TCPI).

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter12: Forecasting Travel Demand
Section: Chapter Questions
Problem 14P
icon
Related questions
icon
Concept explainers
Question

,4

 

A fence 18 feet by 18 feet is being built for $72,000.00 in 4 weeks. During week 2, 30’ feet has been completed and & $36,000.00 has been spent. Calculate the following:
•   Estimate to Completion (ETC)
• Variance at Completion (VAC)
• To Complete Performance Index (TCPI).

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Budget estimating
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning