A contractor has a job which should be completed in 100 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 130 days. Of the 80 men, 50 are each paid P120.00 a day, 25 at P180.00 a day, and 5 at P250.00 a day. For each day beyond the original 100 days, the contractor has to pay P500.00 liquidated damages. a. How many more men should the contractor add so that he can complete the work on time? b. If of the additional men, 2 are paid P180.00 a day, and the rest at P120.00 a day, would the contractor save money by employing more men and not paying the fine and by how much?
A contractor has a job which should be completed in 100 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 130 days. Of the 80 men, 50 are each paid P120.00 a day, 25 at P180.00 a day, and 5 at P250.00 a day. For each day beyond the original 100 days, the contractor has to pay P500.00 liquidated damages. a. How many more men should the contractor add so that he can complete the work on time? b. If of the additional men, 2 are paid P180.00 a day, and the rest at P120.00 a day, would the contractor save money by employing more men and not paying the fine and by how much?
Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
Related questions
Question
A contractor has a job which should be completed in 100 days. At present, he
has 80 men on the job and it is estimated that they will finish the work in 130
days. Of the 80 men, 50 are each paid P120.00 a day, 25 at P180.00 a day, and
5 at P250.00 a day. For each day beyond the original 100 days, the contractor
has to pay P500.00 liquidated damages.
a. How many more men should the contractor add so that he can complete
the work on time?
b. If of the additional men, 2 are paid P180.00 a day, and the rest at P120.00 a
day, would the contractor save money by employing more men and not
paying the fine and by how much?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,