A Contract for an office building includes the provision of a storage tank. Drawing No Q₁ shows the plan and Section of the proposed storage Tank. Take off quantities for the following work Topsoil excauation b) Basement excavcition Filling to basement excauation and replacement of topsoil around the structure Specifications 1 lapsoil to be excavated over the area of the structure for a width of 4m all around same and deposited 15m away for re use 2 Top soil to be excavated to a depth of 150mm 3 Excavate for basement including filling around the structure 4 and remove surplus soil from site Filling is to be of selected excavated material 5) Filling around the structure with topsoil 150mm depth NB use CES MM4 2 20.00 STORAGE TANK 30.00 C 13.00 100 FILL 300- 300 TIIVI 300 PLAN SCALE 1:300 20.0원 1.00' 143.001 300 ORIGINAL SURFACE 12M FILL 110M 300 5M 300 SECTION SCALE 1:200 DRAWING No.Q STORAGE TANK

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
A
Contract for an office building includes the provision
of a storage tank. Drawing No Q₁ shows the plan and
Section of the proposed storage Tank. Take off quantities for
the following work
Topsoil excauation
b) Basement excavcition
Filling to basement excauation and replacement of topsoil around
the structure
Specifications
1 lapsoil to be excavated over the area of the structure
for a width of 4m all around same and deposited 15m away
for re use
2 Top soil to be
excavated to a
depth of
150mm
3 Excavate for basement including filling around the structure
4
and remove surplus soil from site
Filling
is to be of selected excavated material
5) Filling around the structure with topsoil 150mm depth
NB use CES MM4
Transcribed Image Text:A Contract for an office building includes the provision of a storage tank. Drawing No Q₁ shows the plan and Section of the proposed storage Tank. Take off quantities for the following work Topsoil excauation b) Basement excavcition Filling to basement excauation and replacement of topsoil around the structure Specifications 1 lapsoil to be excavated over the area of the structure for a width of 4m all around same and deposited 15m away for re use 2 Top soil to be excavated to a depth of 150mm 3 Excavate for basement including filling around the structure 4 and remove surplus soil from site Filling is to be of selected excavated material 5) Filling around the structure with topsoil 150mm depth NB use CES MM4
2
20.00
STORAGE TANK
30.00
C
13.00
100
FILL
300-
300
TIIVI
300
PLAN
SCALE 1:300
20.0원
1.00'
143.001
300
ORIGINAL SURFACE
12M
FILL
110M
300
5M
300
SECTION SCALE 1:200
DRAWING No.Q STORAGE TANK
Transcribed Image Text:2 20.00 STORAGE TANK 30.00 C 13.00 100 FILL 300- 300 TIIVI 300 PLAN SCALE 1:300 20.0원 1.00' 143.001 300 ORIGINAL SURFACE 12M FILL 110M 300 5M 300 SECTION SCALE 1:200 DRAWING No.Q STORAGE TANK
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning