A -3% grade meets a +5% grade near an underpass. In order to maintain the minimum clearance allowed under the bridge and at the same time introduce a vertical transition curve in the grade line, it is necessary to use a curve that lies 200m on one side of the vertex of the straight grade and 100m on the other. The station of the beginning of the curve (200m) is 10+000 and its elevation is 228m.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
SITUATION 6
A -3% grade meets a +5% grade near an underpass. In
order to maintain the minimum clearance allowed under
the bridge and at the same time introduce a vertical
transition curve in the grade line, it is necessary to use a
curve that lies 200m on one side of the vertex of the
straight grade and 100m on the other. The station of the
beginning of the curve (200m) is 10+000 and its
elevation is 228m.
20. Determine the stationing of the lowest point of the
curve.
Соpy
Ctrl + C
а. 10
b. 10-zuɔu. 1UTZ09
21. Determine the elevation at station 10+040.
a. 227.9c. 226.5
b. 226.7d. 227.1
22. If the uphill edge of the underside of the bridge is at
station10+220 and at elevation 229.206m, what is the
vertical clearance under the bridge at this point?
а. 4.2с. 4.4
b. 4.3d. 4.1
Transcribed Image Text:SITUATION 6 A -3% grade meets a +5% grade near an underpass. In order to maintain the minimum clearance allowed under the bridge and at the same time introduce a vertical transition curve in the grade line, it is necessary to use a curve that lies 200m on one side of the vertex of the straight grade and 100m on the other. The station of the beginning of the curve (200m) is 10+000 and its elevation is 228m. 20. Determine the stationing of the lowest point of the curve. Соpy Ctrl + C а. 10 b. 10-zuɔu. 1UTZ09 21. Determine the elevation at station 10+040. a. 227.9c. 226.5 b. 226.7d. 227.1 22. If the uphill edge of the underside of the bridge is at station10+220 and at elevation 229.206m, what is the vertical clearance under the bridge at this point? а. 4.2с. 4.4 b. 4.3d. 4.1
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Composite construction
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning