A 30-m length of earthwork volume for a proposed road has a constant cross section of cut and fill, in which the cut area equals the fill area. The level formation is 10 m wide. The tranverse ground slope is 20° and the side slope in cut is 0.5 horizontal to 1 vertical. Calculate the volume of excavation in 30 m length.

Fundamentals of Geotechnical Engineering (MindTap Course List)
5th Edition
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter13: Slope Stability
Section: Chapter Questions
Problem 13.28CTP
icon
Related questions
Question
8. A 30-m length of earthwork volume for a proposed road has a constant cross section of
cut and fill, in which the cut area equals the fill area. The level formation is 10 m wide.
The tranverse ground slope is 20° and the side slope in cut is 0.5 horizontal to 1 vertical.
Calculate the volume of excavation in 30 m length.
Transcribed Image Text:8. A 30-m length of earthwork volume for a proposed road has a constant cross section of cut and fill, in which the cut area equals the fill area. The level formation is 10 m wide. The tranverse ground slope is 20° and the side slope in cut is 0.5 horizontal to 1 vertical. Calculate the volume of excavation in 30 m length.
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Knowledge Booster
Measuring sitework, excavation and piling
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning