6- --It is the smallest time taken to complete the activity if everything goes on well A- Most likely time estimate B- Pessimistic time estimate C-Optimistic time estimate. D. None of these 7- -is phase involves setting the objectives of the projeet and the assumptions to be made A- Scheduling B- organizing C Controlling D- Planning 8 - The drawings, conditions, terms, and specifications setting forth the requirements for constructing the project. Refer to A- Quality B- Contract documents C- Project Manual D-All the above 9- To disconnect an activity before the completion of all the activities in a network diagram is known as A- Dangling B- Redundancy C-Looping D-Dummy activity 10- - refers to the amount of time by which the completion of an activity could be delayed beyond the earliest expected completion time without affecting the overall project duration time. A- Critical path B-Free float C- independent float D-Total float Page I of I
6- --It is the smallest time taken to complete the activity if everything goes on well A- Most likely time estimate B- Pessimistic time estimate C-Optimistic time estimate. D. None of these 7- -is phase involves setting the objectives of the projeet and the assumptions to be made A- Scheduling B- organizing C Controlling D- Planning 8 - The drawings, conditions, terms, and specifications setting forth the requirements for constructing the project. Refer to A- Quality B- Contract documents C- Project Manual D-All the above 9- To disconnect an activity before the completion of all the activities in a network diagram is known as A- Dangling B- Redundancy C-Looping D-Dummy activity 10- - refers to the amount of time by which the completion of an activity could be delayed beyond the earliest expected completion time without affecting the overall project duration time. A- Critical path B-Free float C- independent float D-Total float Page I of I
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Hello, I have an exam and I need to answer all the options
![6-
-It is the smallest time taken to complete the activity if everything goes on well
A- Most likely time estimate B- Pessimistic time estimate C- Optimistic time estimate.
D. None of these
7-
-is phase involves setting the objectives of the projeet and the assumptions to be made
A- Scheduling B- organizing
C Controlling D- Planning
8 - The drawings, conditions, terms, and specifications setting forth the requirements for constructing the
project. Refer to
A- Quality
B- Contract documents C- Project Manual
D-All the above
9- To disconnect an activity before the completion of all the activities in a network diagram is
known as
A- Dangling B- Redundancy C-Looping
D- Dummy activity
10-
- refers to the amount of time by which the completion of an activity could be delayed
beyond the earliest expected completion time without affecting the overall project duration time.
A- Critical path B-Free float C- independent float D-Total float
Page I of I](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F924a9a07-c055-4522-960d-e0dc14693f46%2F0ed8f6c7-0ea9-4448-adeb-439d396cc18a%2Fs03djr9_processed.jpeg&w=3840&q=75)
Transcribed Image Text:6-
-It is the smallest time taken to complete the activity if everything goes on well
A- Most likely time estimate B- Pessimistic time estimate C- Optimistic time estimate.
D. None of these
7-
-is phase involves setting the objectives of the projeet and the assumptions to be made
A- Scheduling B- organizing
C Controlling D- Planning
8 - The drawings, conditions, terms, and specifications setting forth the requirements for constructing the
project. Refer to
A- Quality
B- Contract documents C- Project Manual
D-All the above
9- To disconnect an activity before the completion of all the activities in a network diagram is
known as
A- Dangling B- Redundancy C-Looping
D- Dummy activity
10-
- refers to the amount of time by which the completion of an activity could be delayed
beyond the earliest expected completion time without affecting the overall project duration time.
A- Critical path B-Free float C- independent float D-Total float
Page I of I
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning