5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty. Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed. Activities BC Cost to Crash 1 Week P8.000 10,000 8,800 Cost to Crash 2 Weeks P15,000 19,600 19,500 DE EF REQUIRED: a New York Building desires to reduce the normal completion time Job #181 and, at the same time, report the highest possible income for the year. New York Building should crash a. Activity BC 1 week and activity EF 1 week b. Activity DE 1 week and activity BC 1 week c. Activity EF 2 weeks d. Activity DE 1 week and activity EF 1 week b. Compute for the cost to crash of the activities.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

Compute for the cost to crash of the activities.

5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is
currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty.
Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal
completion time of 22 weeks. The following activities can be crashed.
Activities
Cost to Crash 1 Week
Cost to Crash 2 Weeks
P 8.000
10,000
8,800
BC
P15,000
19,600
19,500
DE
EF
REQUIRED:
a New York Building desires to reduce the normal completion time Job #181 and, at the same time, report
the highest possible income for the year. New York Building should crash
a. Activity BC 1 week and activity EF 1 week
b. Activity DE 1 week and activity BC 1 week
c. Activity EF 2 weeks
d. Activity DE 1 week and activity EF 1 week
b. Compute for the cost to crash of the activities.
Transcribed Image Text:5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty. Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed. Activities Cost to Crash 1 Week Cost to Crash 2 Weeks P 8.000 10,000 8,800 BC P15,000 19,600 19,500 DE EF REQUIRED: a New York Building desires to reduce the normal completion time Job #181 and, at the same time, report the highest possible income for the year. New York Building should crash a. Activity BC 1 week and activity EF 1 week b. Activity DE 1 week and activity BC 1 week c. Activity EF 2 weeks d. Activity DE 1 week and activity EF 1 week b. Compute for the cost to crash of the activities.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.