4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the folle incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to whole dollar amount. Loss amounts should be indicated with a minus sign.) Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) 2021 2022 2021 2022 2023 $2,542,000 $3,810,000 $3,210,000 5,658,000 3,110,000 2023

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Do not give image format
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
2021
$2,542,000
5,658,000
2,020,000
1,810,000
2021
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs
incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest
whole dollar amount. Loss amounts should be indicated with a minus sign.)
2022
2022
$3,772,000
1,886,000
4,294,000 3,686,000
4,390,000
3,800,000
2023
$2,074,600
2021
2022
$2,542,000 $3,810,000
5,658,000 3,110,000
2023
0
2023
$3,210,000
Transcribed Image Text:In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) 2021 $2,542,000 5,658,000 2,020,000 1,810,000 2021 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2022 2022 $3,772,000 1,886,000 4,294,000 3,686,000 4,390,000 3,800,000 2023 $2,074,600 2021 2022 $2,542,000 $3,810,000 5,658,000 3,110,000 2023 0 2023 $3,210,000
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
2021
2022
2023
$2,542,000 $3,772,000 $2,074,600
5,658,000
1,886,000
2,020,000
1,810,000
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs
incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest
whole dollar amount. Loss amounts should be indicated with a minus sign.)
2021
2022
4,294,000
3,800,000
3,686,000
4,390,000
2023
2021
2022
2023
$2,542,000 $3,810,000 $3,930,000
5,658,000 4,120,000
0
Transcribed Image Text:[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) 2021 2022 2023 $2,542,000 $3,772,000 $2,074,600 5,658,000 1,886,000 2,020,000 1,810,000 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 4,294,000 3,800,000 3,686,000 4,390,000 2023 2021 2022 2023 $2,542,000 $3,810,000 $3,930,000 5,658,000 4,120,000 0
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Financial Reporting in Hyperinflationary Economies
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education