3-Late start (LS) for events is
Q: ing? What is the importance of linear programming? What is simplex method? What is the purpose of…
A: linear programming
Q: Define the term Slack-Time?
A: Project management can be termed as the application of knowledge, techniques, tools, skills, and…
Q: (a) Construct the AON network for the project. (b) Determine all paths that run from the start to…
A: Activity-on-node is a project management term that leads to a precedence diagramming method that…
Q: Create network diagram (PERT)
A: Given data is
Q: Why is online booking very suitable for organizational event of this type?
A: An online booking is software that allows a customer to book and pay for an activity or service…
Q: 1.what are the major deliveries in the monitoring and controlling phase 2.what are 4 project…
A: During the lifecycle of the project, the monitoring and control phases involve a continuous review…
Q: 2- Find the completion time (TE).
A: TE stands for the expected duration. It means the expected time duration that each activity will…
Q: B. Please draw an activity diagram for the tour reservation.
A: Please find the attachment in next step.
Q: Describe the meaning of slack, and discuss how it can be determined.
A: Project management is the application of processes, methods, skills, knowledge and experience in…
Q: 7-Partial grace period (FF) for events is
A:
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Hi, we are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: Case Study 2: Event Online Booking Systems: Europian Conference on Optical Communication…
A: 1. The online booking system is situatable for conference events because it provides administration…
Q: WBS for construction project?
A: WBS stands for work break structure, which means the grouping of project elements to organize and…
Q: Clarify schedule responsibilities of the controller, management, and teams for the project of…
A: Responsibility has two different senses in the management literature. It explains a duty or task…
Q: ome examples of realized projects today in all over the world. a) Key project managem
A: In one web application, ProjectManager allows you to manage plans, resources, budgets, and teams. To…
Q: Q4/ The table below shows the duration and direct costs for the activities of a construction…
A: Activity Immediate Normal Normal Crash Crash Predecessors Time Cost Time Cost A - 5 2000 3 12000…
Q: a. Find the critical path.
A: A network diagram is a visual representation of a project which identifying the activity…
Q: how can the below control problem be resolve in a business and how does this control problem affect…
A: What causes delivery delays? To figure out how to prevent delivery delays, you must first figure out…
Q: 8. The following information (in AOA format) concerns progress at day 40 of an Internet marketing…
A: The overall project does not seem to be in control based on time and cost: Activity 1-2: This…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Project length is the evaluation of the amount of time needed by a specific project activity carried…
Q: 6- The total grace period (TF) for events is
A: Total float is the time for which the individual activities can be delayed without delaying the…
Q: a. Determine the optimum time-cost crashing plan. Continue crashing as long as the total crashing…
A: Possible paths Duration 1-2-5-7-11-13 = 5+8+7+4+11 = 35 1-3-8-11-13 = 4+12+5+11 = 32…
Q: Should BestLine’s ordering department have been more involved during the project?
A: Every project has its basic requirements for it to be successfully completed. Every project should…
Q: The table below shows a schedule. Activity Duration Predecessor Cost of crashing Max. days it can be…
A: Draw Network Diagram :
Q: PROJECT PLANNING & SCHEDULING WITH PERT/CPM Given the activities of a project; their optimistic…
A: Given data is
Q: Part III Project management Event management is defined as a well-planned and organized occasion…
A: COVID-19 has had an impact on almost all phases of life. Many businesses that were growing before…
Q: determine the following: -Normal cost -additional cost -maximum crash time for activity A
A: In the table data, we have activity data, the normal duration and accelerated duration of each…
Q: Create a proposal on Hospital management system Plan Section *Project schedul
A: A Hospital needs a proper management system to coordinate their employees, communicate with doctors,…
Q: A mental picture that you have and want to turn into a reality in the future refers to A. Plan B.…
A: C. Vision
Q: In project management why is float important?
A: Project management is the process of directing a group of people to a common goal based on the…
Q: (b) Identify all of the paths on the network diagram and note how long they are, using Figure 6- 8…
A:
Q: How is slack/float calculated? Latest finish date – duration Latest start date –…
A: THE ANSWER IS AS BELOW:
Q: Explain the term Crash Project?
A: A project is a series of actions or activities that are completed in order to accomplish specific…
Q: Briefly describe each of these priority rules:a. FCFS
A: FCFS (First come first serve) is a priority rule based giving preference to consumers coming…
Q: What are the types of project risk that may occur while implementing ERP project in a company?
A: ERP Project: ERP stands for Enterprise Resource Planning which was widely used in…
Q: 448 Activity D F 24. Office Automation, Inc., developed a proposal for introducing a new…
A:
Q: Draw the Network diagram and include the Early Starts (ES), Early Finishes (EF), Late Starts a.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Step by step
Solved in 2 steps with 2 images
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity D. Activity B is connected to activity E. Activity C is connected to activity F. Activity D is…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a). Develop a project network. (b) Develop an activity schedule. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F (c) What are the critical activities? (Enter your answers as…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity E. Activity C is connected to activity D. Activity D is…
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost? (A, B, C, D, E) = (e) Develop an activity schedule for the crashed project. Activity EarliestStart LatestStart…The ideal outcome of the planning process group is to complete a project successfully by delivering the agreed-upon project scope within time, cost, and quality constraints Select one: True False Initiating involves developing a project charter, which is part of the project ______ management knowledge area. Select one: a. scope b. risk c. communications d. integration Estimate activity resources output Select one: a. Activity list, activity attributes, milestone list, project management plan updates b. Project schedule network diagrams, project documents updates c. Activity resource requirements, resource breakdown structure, project documents updates d. Schedule management plan As time progresses, the scope of a project should become ... Select one: a. more clear and specific b. more vague c. more ambiguous d. more difficultOffice Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop an activity schedule. What are the critical activities? (Enter your answers as a comma-separated list.) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes…
- 1 Cara's clients, Emily and Dave, have just had a baby and she would like to do something nice for them. She signs them up for a baby registry that sends them a small gift. Emily and Dave will be sent information and service lists that are geared toward helping new parents. She provided their names, address and phone numbers so that they will not miss any of the activities provided in the package. Has Cara dealt with her clients appropriately? NUYLOTNQhObm1bEVKUTO90 a0 Cara did not protect her clients' privacy when she shared their personal information with the baby registry. O Cara should not make this a regular practice. Her clients will begin to expect gifts and she will not be able to sustain this. CO Cara should have set up an appointment to re-evaluate her clients' needs now that they have had a baby. 40 Cara's gift is very thoughtful and will help to build a relationship with her clients. NUTYks10TNRUQ2h0bmkbEVKUTO90In the space provided below create the network diagram that shows the relationship (logic) of project activities shown below and then number each event. 1. In a given project activities "A, B and C are initial activities that may begin at the same time 2. -----"D" cannot begin until "A" is complete. 3. ----- "B" must be complete before E can begin. 4. ----- "F" cannot start until "C" is finished. 5. ----- "G" cannot begin until "B" is finished. 6. ----- "G" and "D" must be done before "H" can begin. 7. ----- "I" cannot begin until "B" is finished. 8. ----- "J" can begin only after "F" and "I" are complete. 9. ----- Once "E" is complete, "K" can begin. 10. ---- The project will be finished when "H" "J" and "K" are complete.Opp l +O 90% 10:31 33,19 K/s UNIVERSITY OF GHANA 35 Part 1 of 1- Question 1 of 100 . refers to how the project is expected to work and solve the stated problem in project or proposal writing. A. Project Portfolio B. Portfolio of Activities C. Plan of Activities D. Project Activities Reset Selection [1] Question Progress
- Image of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.++ Earned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: Table 2 No 1 2 3 Type Cumulative Budgeted Cost (CBC) Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) TOTAL RM 64,000 68,000 54,000 100,000 Percentage 64.0 68.0 54.0 100.0 a) With the aid of a typical S-curve diagram, draw and explain the four cost-related measures such as TBC, CBC, CAC and CEV to analyses the overall project cost performance.You are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.