#21 ToolTime has a standard of 2 hours of labor per unit, at P12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of P46,970. ToolTime’s labor price variance is Group of answer choices P770 U. P800 U. P1,030 F. P1,930 F. 22. ToolTime has a standard of 2 hours of labor per unit, at P12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of P46,970. ToolTime’s labor quantity variance is Group of answer choices P770 U. P1,030 F. P1,800 F. P1,930 F.
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
#21
ToolTime has a standard of 2 hours of labor per unit, at P12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of P46,970.
ToolTime’s labor price variance is
Group of answer choices
- P770 U.
- P800 U.
- P1,030 F.
- P1,930 F.
22.
ToolTime has a standard of 2 hours of labor per unit, at P12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of P46,970.
ToolTime’s labor quantity variance is
Group of answer choices
- P770 U.
- P1,030 F.
- P1,800 F.
- P1,930 F.
Step by step