2) Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded Regular Crash Regular Crash By A 6 days | 2 day $2000 $3800 В 12 2000 10000 C A 4 1000 4000 2400 AC00

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

2) Following is a table listing the project activities, sequencing requirements and other relevant information:



Expected Time Direct Cost
Activity Preceded By Regular Crash Regular Crash
A -- 6 days 2 day $2000 $3800
B -- 12 6 2000 10000
C A 4 2 1000 4000
D B, C 10 6 3400 4600
E D 8 6 2800 3900
F E 6 2 5000 7600
G B, C 18 8 16000 19600
H F, G 6 4 2000 4000

(a) Construct a network including the Early and Late Start and Finish times.

(b) Identify the normal Critical Path(s) and the normal expected completion time (c) Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?

2) Following is a table listing the project activities, sequencing requirements and other
relevant information:
Expected Time
Direct Cost
Activity
Preceded
Regular Crash | Regular Crash
By
A
6 days
2 day
$2000
$3800
--
В
12
6.
2000
10000
--
A
4
2
1000
4000
D
В, С
10
6.
3400
4600
E
D
8
6.
2800
3900
F
E
5000
7600
G
В, С
18
8.
16000
19600
H
F, G
6.
4
2000
4000
(a)
Construct a network including the Early and Late Start and Finish times.
(b)
Identify the normal Critical Path(s) and the normal expected completion
time (c) Can the project be crashed to last 18 days? Which activities
should be crashed and at what additional cost?
Transcribed Image Text:2) Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded Regular Crash | Regular Crash By A 6 days 2 day $2000 $3800 -- В 12 6. 2000 10000 -- A 4 2 1000 4000 D В, С 10 6. 3400 4600 E D 8 6. 2800 3900 F E 5000 7600 G В, С 18 8. 16000 19600 H F, G 6. 4 2000 4000 (a) Construct a network including the Early and Late Start and Finish times. (b) Identify the normal Critical Path(s) and the normal expected completion time (c) Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.