100 MW solar farm, build cost is $0.8/W, lifetime is 25 years, ITC = 25%, Capacity Factor is 24%, O&M = $20/W-yr, Interest rate = 5% What is the LCOE of this solar farm? %3D

Electricity for Refrigeration, Heating, and Air Conditioning (MindTap Course List)
10th Edition
ISBN:9781337399128
Author:Russell E. Smith
Publisher:Russell E. Smith
Chapter17: Commercial And Industrial Air-conditioning Control Systems
Section: Chapter Questions
Problem 6RQ
icon
Related questions
Question
100 MW solar farm, build cost is $0.8/W, lifetime is 25 years, ITC = 25%,
Capacity Factor is 24%, O&M = $20/W-yr, Interest rate = 5%
What is the LCOE of this solar farm?
%3D
Transcribed Image Text:100 MW solar farm, build cost is $0.8/W, lifetime is 25 years, ITC = 25%, Capacity Factor is 24%, O&M = $20/W-yr, Interest rate = 5% What is the LCOE of this solar farm? %3D
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Solar cell
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Electricity for Refrigeration, Heating, and Air C…
Electricity for Refrigeration, Heating, and Air C…
Mechanical Engineering
ISBN:
9781337399128
Author:
Russell E. Smith
Publisher:
Cengage Learning
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning