1.) Draw the network using the table above. Your work should look similar to slide 44 in the Module 10 notes (D2L). Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

The second picture is an example of how it should look like. Please help confused on what to do.

Start
N
B
CE
C
D
4
A
8
+
A
∞
∞
4
10
F
G
13
13
13
13
13
I
N
15
15
Transcribed Image Text:Start N B CE C D 4 A 8 + A ∞ ∞ 4 10 F G 13 13 13 13 13 I N 15 15
PERT/CPM HOMEWORK (MOD 10)
In the table below, you will see activities and times associated with each activity. Review the
PowerPoint slides in Module 10 (D2L), before you start this assignment.
Task
A
B
с
D
E
F
G
Preceding
Tasks
NONE
NONE
A
A
B
с
D.E
to (optimistic)
2
2
1
4
4
3
1
tm (most likely)
3
3
2
6
5
4
1
ta
(pessimistic)
10
4
3
14
12
5
7
1.) Draw the network using the table above. Your work should look similar to slide 44 in the
Module 10 notes (D2L). Make sure all 4 values (ES, EF, LS, LF) are listed on the network.
2.) What is the slack for each activity? What is the critical path? Show ALL of your work!
3.) Find the expected project completion time. What is the project variance?
4.) What is the probability that it would be in more than 14 days? Show ALL of your work.
Transcribed Image Text:PERT/CPM HOMEWORK (MOD 10) In the table below, you will see activities and times associated with each activity. Review the PowerPoint slides in Module 10 (D2L), before you start this assignment. Task A B с D E F G Preceding Tasks NONE NONE A A B с D.E to (optimistic) 2 2 1 4 4 3 1 tm (most likely) 3 3 2 6 5 4 1 ta (pessimistic) 10 4 3 14 12 5 7 1.) Draw the network using the table above. Your work should look similar to slide 44 in the Module 10 notes (D2L). Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance? 4.) What is the probability that it would be in more than 14 days? Show ALL of your work.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 10 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.