1.) Draw the network using the table above. Your work should look similar to slide 44 in the Module 10 notes (D2L). Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance?
Q: What are your thoughts for the B-Corp model? Would you apply and if so why or why not?
A: The importance of balancing social and environmental needs for business is that it helps in…
Q: For this assignment you must pick 4 processes – one from each of the knowledge areas listed below.…
A: Project management is the discipline of planning, organizing, and controlling resources to achieve…
Q: A project consists of seven activities and the time estimates of the activities are furnished as…
A: A project has 7 activities with 3 time estimates:ActivityOptimistic DaysMost Likely DaysPessimistic…
Q: There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Each…
A: We must locate the critical path(s) and crash the operations on them in order to calculate the most…
Q: Warrenia has two regions. In Oliviland, the marginal benefit associated with pollution cleanup is MB…
A: Marginal BenefitOliviland MB = 300 – 10QLinneland MB = 200 – 4QMarginal cost of cleanup = $12 per…
Q: South Africa’s logistics group Transnet gradually resumed operations at its Durban port on Wednesday…
A: The present case relates to the Durban port which has experienced severe flooding due to heavy…
Q: LM.53 In an effort to reduce costs, many regional power companies want to lower their safety stock…
A: Inventory management refers to the process of overseeing and controlling the flow of goods or…
Q: Help me in my group project, plese give me Idea My project: The use of modern methods to reduce…
A: When evaluating the success of a project focused on reducing carbon emissions in the construction…
Q: What are the keys to successfully implementing an ERP system?
A: Enterprise Resource Planning (ERP) system implementation is a complex and crucial endeavor for any…
Q: Do you think that the growth of automation is to blame for the increase in knowledge workers?
A: The growth of the automation, driven by advancements in the technology, has had the significant…
Q: From the case study titled "Half a Century of Supply Chain Management at Walmart" published by Ivey…
A: The 2013 Ivey Publishing case study titled "Half a Century of Supply Chain Management at Walmart"…
Q: Rosaliz has been working for ten years in a food and institutional product distribution company that…
A: Supplier management refers to the processes and activities involved in effectively managing the…
Q: Please use the following information for questions #1-5. Knights Corporation, a leader in…
A: Economic Order Quantity or EOQ (Q*) is the optimal quantity of inventory required that helps in…
Q: How do you calculate 2.282 and 0 for the UCL and LCL
A: R chart is used to check the process variationsR-chart control limits:UCL =D4* Mean of the ranges =…
Q: Colonial State College is considering building a new multipurpose athletic complex on campus. The…
A: An activity diagram in project management depicts the flow of activities in the order and sequence…
Q: What is the rationale behind the utilization of ISO by systems developers?
A: ISO (International Organization for Standardization) develop a set of guidelines and parameters of…
Q: Which of the following statements regarding PERT analysis is true? Each activity has two…
A: PERT (Program Evaluation and Review Technique) analysis is a project management tool used to…
Q: XYZ company is a subcontractor of the ABC company. XYZ manufactures items and directly sells them to…
A:
Q: A restaurant uses 100 per week or 5,000 quart bottles of ketchup each year. The ketchup costs $3.00…
A: Given:The annual demand is given as 5,000 quart bottles of ketchup, which is D = 5,000. The ordering…
Q: The A&M Hobby Shop carries a line of radio-controlled model racing cars. Demand for the cars is…
A: The economic order quantity -(EOQ) is an organization optimal order quantity that fullfill demand…
Q: A market is people or organizations with needs or wants and with the ability and the willingness to…
A: A consumer is an individual or a household that purchases goods or services to satisfy their…
Q: Give explanation related to systems, manufacturing systems, industrial systems, service systems and…
A: A system includes several components that cooperate to achieve a single goal. Imagine an…
Q: The purchasing function in corporate business is a team effort. Critically discuss the buying…
A: In business environments, the buying function is a team effort that is essential to achieving…
Q: Amazon finds that sales in July are much greater relative to other months because of the Amazon…
A: If sales are increased due to some sale where heavy discount is given, in order to predict next…
Q: The specification for a plastic liner for concrete highway projects calls for a thickness of 6.0 mm…
A: Mean (X) = 6.03Standard deviation Upper specification limit (USL) = Lower specification limit (LSL)=…
Q: Why should a systems developer care about ISO?
A: ISO is an independent, non-governmental international organization that develops and publishes…
Q: Case Study 1: How a Strategy Change Led to Nike’s Formation Nike, the world’s most famous athletic…
A: Strategy implementation is the process of translating strategic plans into action. It involves…
Q: Develop a project network. (b) Develop an activity schedule. Activity Earliest Start Latest Start…
A: Here, each activity is given with description data, immediate predecessor data, and normal time, as…
Q: Examine the factors that drive technological change in organizations. Assess your organization…
A: Organizations consider new technologies, they implement such technologies for many reasons. Here,…
Q: Use this data to determine the correlation between time on the diet and weight loss (either the…
A: Here, for each customer, I have been given the time and weight loss data, I would determine the…
Q: A small parts manufacturer has just engineered a new product for the automotive industry. In order…
A: Usually we know only the states of nature and the probabilities of the state of nature. But we do…
Q: In the context of Transnet motivate why the organisation should have a functional operations…
A: Transnet is a major South African state-owned company that specialises in the transportation and…
Q: How can organizations use benchmarking as a tool to drive Total Quality Management improvement…
A: Total Quality Management (TQM) is a comprehensive management approach aimed at achieving continuous…
Q: The University of Miami bookstore stocks textbooks in preparation for sales each semester. It…
A: A probability model decision analysis is a framework used to make decisions under uncertainty by…
Q: Although organisations in the manufacturing sector usually carry more inventory than service firms,…
A: 1. Meeting client Demand: Having inventory enables businesses to have things on hand to satisfy…
Q: Jody of Jody’s Custom Tailoring is considering expanding her growing business. The question is…
A: A decision tree is a graphical representation of a decision-making process or a decision problem.
Q: Toys "R" Us had cost of goods sold of $12,355 million, ending inventory of $3,187 million, and…
A: Given that:COGS12355Ending Inventory3187Average Inventory turnover2343
Q: What precisely is meant by the term "dynamic programming," and how does the procedure to which it…
A: Dynamic Programming is a problem solving technique which is basically used in the field of…
Q: The Denver International Airport baggage system crash may have been caused by bad software project…
A: Project management is the discipline of planning, organizing, and managing resources to successfully…
Q: 10. In the following MRP planning schedule for item J, indicate the correct net requirements,…
A: Item J:Lead time = 1 weekOn hand inventory = 40The given problem is for Material requirements…
Q: Operations management consulting services?
A: Operations management consulting services are the professional advisory services provided to…
Q: Examine and analyse in depth the maritime security areas of cargo theft
A: Maritime security can include the policies, and actions that are taken for protecting and safeguard…
Q: Munson Performance Auto, Inc., modifies 475 autos per year. The manager, Adam Munson, is…
A: Using the aforementioned information, I would calculate the multi-factor productivity metric.
Q: What do you think are the most significant factors that are affecting the quality of the work in the…
A: First, I would discuss the most significant factors affecting the quality of the work in the…
Q: Bindley Corporation has a one-year contract to supply motors for all washing machines produced by…
A: Linear programming helps us to find the optimal solution/best outcome, with the given constraints.We…
Q: Please do not give solution in image formate thanku. True or False Collaborative leadership is…
A: Leadership is the ability of an individual as well as a group to influence other people working in…
Q: The term "FMS option" raises a number of questions.
A: The term "FMS option" refers to a particular domain or industry-specific concept or characteristic.…
Q: An order for 150 units is processed on work centers A and B. It is decided to over lap A and B by…
A: Manufacturing lead time is the time taken in delivering the final product to the customers. It is…
Q: Give typing answer with explanation and conclusion What are CrossFit’s core competencies that give…
A: The sustainable competitive advantage refers to the set of qualities as well as resources of a…
Q: Loading A. never considers process capacity. B. is the process of assigning jobs to work or…
A: Process capacity planning is an important concept that helps in optimizing and managing the…
The second picture is an example of how it should look like. Please help confused on what to do.
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 10 images
- Evaluate the below statement according to the project management terminologies and choose the correct answer: It is the process of making a forecast or precise approximation Choose... of time and cost associated with a work package or activity. Graphically describes a project consisting of well-defined Choose.. activities, the completion of which marks its end. One of the Perform Quantitative Risk Analysis process has a Choose.. Tools and Techniques. Useful for building accountability through assigning specific Choose.. tasks to team members. It is the standard format each path through the network must be continuous with no gaps, discontinuities, or dangling Choose... activities. Organizational Assets, Project Scope Statement, Cost Management Plan and Schedule Management Plan are inputs Choose.. of: Choose... Work Breakdown Structure Expert Judgment Bar chart Estimating A horizontal diagram format Plan Risk ManagementYou are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.Martha has been assigned a team of 10 people to help her plan a major customer appreciationevent. They have been working together for over a month now and they just haven’t really cometogether as a team. She was sure she started off well. She contacted each individual on the teamand let them know their responsibilities on the project. Each of the members gets the taskscompleted, but don’t seem concerned with the others on the team. If someone needs help, no onepitches in to assist. If a team member has a problem, no one helps him to solve that problem. Justyesterday one of the team members had an emergency and asked if someone on the team couldhave a call with the sales team so she could leave early. No one offered to help so Martha jumped in to assist. Martha had to do something. This was a bad experience for everyone frankly and somefolks already were talking about getting off the project. Plus she felt the event won’t be as good asit could if they just came together as a team. In…
- PERT/CPM HOMEWORK (MOD 10) In the table below, you will see activities and times associated with each activity. Review the PowerPoint slides in Module 10 , before you start this assignment. Task Preceding Tasks to (optimistic) tm (most likely) tp (pessimistic) A NONE 2 3 10 B NONE 2 3 4 C A 1 2 3 D A 4 6 14 E B 4 5 12 F C 3 4 5 G D,E 1 1 7 1.) Draw the network using the table above. Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance? 4.) What is the probability that it would be in more than 14 days? Show ALL of your work. *The circle diagram picture is just an example of how it should look it is not apart of the problem in the chartFor this assignment, you will design a risk management plan for a project titled “prolonged waiting times for patients in a large outpatient hospital” that will include the following elements: Risk Register/Matrix (list of at least 5 (five) risks along with the associated impact and probability scores along with risk score) Contingency plan (list of any risks you will plan for in advance along with what triggers the contingency). Be sure to include any information useful to stakeholders on the rationale for the creation of these elements as well as any outside references supporting the risk management plan.Do Homework - Chapter 8 Homework Profile 1 Microsoft Edge Ohttps://mylab.pearson.com/Student/PlayerHomework.aspx?homeworkld%3619835558&questionld%3D18&flushed%-Dfalse&cld%3D6866071¢erwin=Dyes BBA 370 spring 22 Hunter Mccoy 03/20/22 8:52 PM Homework: Chapter 8 Homework HW Score: 18.18%, 2 of 11 stio = Question 5, Problem 8.5 points O Points: 0 of 1 Part 1 of 2 Save Subway, with more than 27,000 outlets in the U.S., is planning for a new restaurant in Buffalo, New York. Three locations are being considered. The following table gives the factors for each site. Factor Weight Maitland Baptist Church Northside Mall Space 0.25 55 75 85 Costs 0.25 35 85 35 Traffic density 0.20 50 80 65 Neighborhood income 0.15 45 75 40 Zoning laws 0.15 75 25 85 a) Based on the given information, the best location in Buffalo for Subway to open the new restaurant is with a total weighted score of (Enter your response rounded to two decimal places.) Northside Mall Baptist Church Maitland Clear all Check…
- Case Study The CEO of your company needs to employ a personal assistant for helping him to manage his schedules and in meetings. The CEO needs an office Assistant to oranize various files and document n his office. The assistant will be responsible to book tickets for the CEO for his business rips home and abroad. The assistant will be required to wrie e-mails on behalf o the CEO. Moreover, he or she will be responsible for wrtng meeting minutes. You are the Manager of HR. The CEO wants you to post a vacancy announce on newspaper to find a suitable Personal Assistant/ Ofice Assistant. The CEO wants to hire someone wih exclient command over writing and spoken English, good speed in typing, two years of work exprience in similar position. The ideal candidate should not be over 25 years old. You will conduct job analysis for the post of personal assistant and publish a vacancy announcement on local newspaper. a)What will be the elements of Job description in the vacancy announcement?…A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Optimistic Time (hr) Most Probable Time (hr) 4 4 0.5 2 3 5 5 Сл 1 3 7.5 Pessimistic Time (hr) 6 6 1.5 10 9 Naturally, the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. (a) Construct the PERT/CPM network for this problem.You are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track? Activity Time Immediate Predecessor A 10 Weeks None B 6 Weeks A C 7 Weeks A D 6 Weeks B E 8 Weeks C F 3 Weeks D G 4 Weeks F
- Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. (b) Develop an activity schedule. (Round your answers to two decimal places.) (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project…Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. (b) Develop an activity schedule. (Round your answers to two decimal places.) (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project…What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A C