For this, Red Planet consultant shall setup esri Environment with necessary back up of all databases, Data and Web Services.
Following activities will be taken care during environment setup.
Uninstall Existing ArcGIS Server Version 10.3 software, applications and service.
Before we upgrade your ArcGIS Server site, ensure that the databases you use are supported at the upgraded ArcGIS Server release such as Microsoft SQL Server database requirements.
• Install supported version of Microsoft SQL version
• Install Latest version of ArcGIS server 10.4.1
• Restore all functionality to ArcGIS Server 10.4.1
Following steps will be taken care will upgrading Application and Services
As part of the upgrade Red Planet would perform the following activities:
…show more content…
5.5 Quality Control
Red Planet retains a tight control on the Quality of its deliverables.
Throughout the implementation phase, Red Planet will conduct periodic reviews of the progress to ensure that the progress of each functional element is in line with the expected deliverables. The pre-defined requirements will be used as a yardstick to do this evaluation.
Any deviation identified during the evaluation is analyzed and classified into one of the three buckets:
• System Driven Anomaly: In this case, the deviation is due to the limitations that are inherent in the system. In this case, Red Planet would, after thorough study, inform Cecil County about the same and present the possible impacts of the anomaly. This would be followed by a detailed discussion with Cecil County to find a workaround to meet the stated requirement.
• Implementation Anomaly: In case the deviation is identified to have resulted from implementation, Red Planet would take immediate steps to employ corrective measures to rectify this anomaly.
The overview of the proposed Quality Control methodology is provided in the diagram below:
5.6 Production
…show more content…
The proposed roll-out dates for production implementation are submitted to the client.
5.7 Training
Training manuals will be created for all the upgraded products. This training manual would be developed right through the development, testing and into the training phase of the project.
The Training would consist of the following
Training program is being developed by Ramses Meza, no update was provided for the task.
The issues presented in these two letters both provide strong cases. However, in my opinion I feel the evidence found in the second letter is much more convincing than the first.
At the end of the training you should be able to understand the following items (Ferrell, Fraedrich & Ferrell, 2008);
Training methods varies as per the, time constraint, existing skills of the user, availability of the instructor, system complexity and many more organizational factors. Few common training methods are:
What do you change in the system so you can ensure the problem won’t be overlooked?
This problem cannot be easily fixed. In order to fix it, we will need not just
Anomaly: Refers to unnatural formations and artifacts caused by “Anomaly Causing Phenomena” (ACP for short). They are sought after by the Underground (q.v.) and the RGA (q.v.) as a source of income. The ACPs which they are formed are invisible to the naked eye, and require the introduction of concentrations of iron for them to create Anomalies. Unknown to the general
Errors are inevitable we are all humans, which means we can all make mistakes. We can, however, try and prevent them to the best of our ability. Staying with the customary system is a surefire way of causing error. For example, in 1999 the scientists at NASA crashed a mars orbiter, costing them 125 million dollars, because the two countries involved in the project were using different systems. The orbiter came too close to mars and after 286 days of preparation and waiting. This could have been avoided if America was On the same system as the other country
Measurable – All tasks will be listed, allocated and assigned to the most appropriate person within the Quality department. Expected completion dates will be set, weekly progress meeting held to monitor the project and the associated tasks. The goal is to complete all the tasks by the 31 January 2013.
The system in question has been around since the beginning of the development of advanced civilizations and has found
Thus, when agencies feel they need “authority to undertake new projects or activities” during a continuing resolution, they should seek an anomaly. The request can either be sent by the agency “directly to Congress,” or it can be routed “through the President and OMB.” However, while anomalies seem to be the answer to avoid new start prohibitions, in reality, the granting of anomalies are rare. For example, in the 2017 Continuing Resolution, there was only one anomaly granted to the DoD, which was approved and codified in Section
The main problems with the existing system and goals for the future system identified as below:
Given consideration to all of the known information given to this evaluator and the multiple
The training is for all user levels i.e. beginners, intermediate and advanced. The trainer will be come up with a proposed training schedule that will encompass all the levels of training and will be subject to approval by Miller Inc, the trainer will at the end of each class give each student a survey that will be used for evaluation and the trainer shall take the class attendance at the start of
3. Values Scan. Analysis is necessary to identify the deficiencies and errors that need modification.