Activity-On-Noon Diagram Essay

Satisfactory Essays

The scope of the fourth assignment is to create the Activity-on-Node (AON) diagram. We continue to use the case from previous assignments. This case of study was supplied by Professor Daniel Baumgartner.
Assignment
Diagram 1 displays the Activity-on-Node diagram. The critical path is identified by the blue dash line. The total shortest time to finish the project is 786 hours, equivalent to 98.25 days. EOC requested to finish the project in 6 month, equivalent to 120 working days.