Unit weight
120 lb/cf
3240 lb/CY
Mat W Correction Factor
0.71
Scraper Load Time
0.75 min
45 sec
16)
1. Max Ideal Production
200 LCY/hr
Material Weight
2000 lb/LCY
Distance
250 f
Grade
10 %
Swell
8%
O & O Cost
$200 /hr
Wages
$50 /hr
1.15
3. Operator Adjustment
0.75
0.8
5. Dozing Technique
1
6. Visibility Adjustment
0.8
7. Efficiency Factor
0.75
10. Grade Correction Factor
0.8
11. Product of Adjustments
0.3312
12. Dozer Production
66.24 LCY/hr
Production (BCY/hr)
61.33 BCY/hr
Total Cost
$250 /hr
BCY Cost
$4.08 17)
Distance
Step 2
Step 3
Step 4
Step 5
(ft)
RR %
GR %
TR %
Speed (mph)
Load
Acc
100
6.5
3.3
9.8
5
Haul
2300
6.5
3.3
9.8
6
Acc
100
6.5
3.3
9.8
5
Dump
Fill
Acc
100
6.5
-3.3
3.2
5
Return
2300
6.5
-3.3
3.2
33
2. Material Weight Correction Factor
4. Material Type Correction Factor