©Dr. Ahmad Jrade 1 Civil Engineering CVG 4173A Construction Management Group Case Project Fall 2019 XYZ Manufacturing Inc. is one of the leading manufacturers of steering wheels, air bags, and shift levers. Located in Oakville, Ontario, XYZ provides services to some of the largest car companies in the world such as, Toyota, Ford, Nissan, and General Moto
rs. The company’s ever-
growing need for production has resulted in the greater need for warehouse and manufacturing space. Currently, XYZ Manufacturing Inc. is interested in building an additional 80,000 square foot warehouse to accommodate these needs. The 80,000 square foot addition in Oakville, Ontario will be added to an existing 194,000 square foot facility. This addition will provide adequate space for state-of-the-art equipment essential to the growing needs of the company. Located on the south east corner of the existing site, the addition will not only provide work space but also additional parking for new employees. To carry out the construction, a section of existing hot mix asphalt will have to be removed along with other site obstructions. The proposed building will allow XYZ Manufacturing Inc. to stay competitive in their area of expertise. As an expert, XYZ Manufacturing Inc. would like you to use the provided 3D model (Autodesk Revit 2018 version) and specifications to generate a report that contains details about the following requirements: •
Identify the quantities of material required for construction, •
The total cost of the project,
©Dr. Ahmad Jrade 2 •
The scope of the work by using a compatible WBS and by identifying all the associated work packages needed to build the warehouse, •
A work plan that shows the sequence of execution (sequential order of the construction activities), •
The construction time required to finish the project. To ease the difficulty of this case study, the assigned groups will need to complete the following modules in due course. This will help you overcome carried forward mistakes especially since all the case components are dependent on each other. Also, this will allow groups to correct or modify any items before the final submission. Each group may have different answers, and thus the grading is based on the methodology followed. Use the provided model to complete the following: •
Module 1 (Due on 05 November 2019)
: o
Create a WBS that will help determine the scope of all the project work, o
Calculate excavation and backfilling quantities, o
Calculate a preliminary cost estimate by using R. S. Means, o
Create a quantity takeoff list for all items, •
Module 2 (Due on 19 November 2019)
: o
Determine the machinery required in excavation and backfilling, o
Identify the productivity of each machine and determine the time required to operate each machine based on quantities, o
Calculate the remaining quantities and the costs required for the whole work packages (identified in the WBS), •
Module 3 (Due on 3 December 2019)
: o
Identify the labor crews required by each work package (identified in the WBS), o
Identify the crew size required for each work package, o
Identify the productivity of each crew per package, o
Identify the time required to construct each work package based on the calculated productivities, o
Develop a network using MS project (based on the WBSs) that indicates the time for each work package, o
Calculate the probability of finishing the project within the calculated duration,
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
Recognize the different types of equipment used in the railroad industry
arrow_forward
I need the answer as soon as possible
arrow_forward
(show your formula)
Given the figure above, compute for the 24-Hour Traffic of Passenger Car: *
A.None of the above
B.72
C.87
D.85
E.102
arrow_forward
History of Autodesk AutoCAD
arrow_forward
Prove that the equation on the left is equal to the equation on the right
arrow_forward
Which of the following is one of the two primary causes of accidents?
a. unmaintained tools
b. hazardous materials
c. unsafe environment
arrow_forward
SOLVE 4.2 ONLY
arrow_forward
List 4 ways metallurgy can help make roads better.
arrow_forward
What do you know about the CHEMFLO 2000 model?
arrow_forward
%VE l1. ?
Assignment 1.JPG →
Evaluate each of the following and express with SI units having an
appropriate prefix: (a) (50 mN)(6 GN), (b) (400 mm)(0.6 MN)²,
(c) 45 MN /900 Gg.
II
arrow_forward
Q19.
Q20.
Q21.
Which are the followings technologies inclusive in Industrial Revolution 4.0
A. Pre-fabrication and Modular Construction
B.
Advanced Building Materials
C. Building Information Modelling
D. All of the above is correct
Which of the following is best describe BIM timeline Level 2
A. Full integration. Full collaboration and full integration in a cloud-based
environment. Include Asset Life Cycle and Facilities Management(7D)
Low Collaboration. Computer Aided Design (CAD) is used to create
drawings. Paper and prints are shared with the team.
Full Collaboration. Adds additional dimensions such as Time
Management and Budget Calculation. Full collaboration and partial
interoperability through the use of distinct CAD model.
D. Partial Collaboration 2D drafts are combined with 3D models in a
Common Data Environment (CDE). Limited collaboration.
B.
C.
Which of the followings statement describes about the Life Span of product in
decision making for a project?
I.
II.
IV.
A.
B.
C.
D.…
arrow_forward
i need the answer quickly
arrow_forward
For the first line of calculation: why VA+VD= 1/2xWxL
I think it should be VA+VD=-1/2xWxL according to sign convention
arrow_forward
As a Civil Engineer, you are to design your own equipment or device. What is this equipment or device? What metals of metal alloys you would prefer to use on it and why?
arrow_forward
4 ways metallurgy can help make roads better. (With references).
arrow_forward
48. It facilitates business development opportunities and a competitive marketplace through market
development, trade promotion, trade shows, domestic and international advocacy, and standards
development.
a. ISO
b. ANSI
c. ITU-T
d. TIA
arrow_forward
Identify and discuss the importance of farm tractor in agriculture.
arrow_forward
How did you get the average cost for this question?
the question is from (Engineering economics analysis, p39)
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,
Construction Materials, Methods and Techniques (M...
Civil Engineering
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:Cengage Learning
Related Questions
- %VE l1. ? Assignment 1.JPG → Evaluate each of the following and express with SI units having an appropriate prefix: (a) (50 mN)(6 GN), (b) (400 mm)(0.6 MN)², (c) 45 MN /900 Gg. IIarrow_forwardQ19. Q20. Q21. Which are the followings technologies inclusive in Industrial Revolution 4.0 A. Pre-fabrication and Modular Construction B. Advanced Building Materials C. Building Information Modelling D. All of the above is correct Which of the following is best describe BIM timeline Level 2 A. Full integration. Full collaboration and full integration in a cloud-based environment. Include Asset Life Cycle and Facilities Management(7D) Low Collaboration. Computer Aided Design (CAD) is used to create drawings. Paper and prints are shared with the team. Full Collaboration. Adds additional dimensions such as Time Management and Budget Calculation. Full collaboration and partial interoperability through the use of distinct CAD model. D. Partial Collaboration 2D drafts are combined with 3D models in a Common Data Environment (CDE). Limited collaboration. B. C. Which of the followings statement describes about the Life Span of product in decision making for a project? I. II. IV. A. B. C. D.…arrow_forwardi need the answer quicklyarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Solid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,Construction Materials, Methods and Techniques (M...Civil EngineeringISBN:9781305086272Author:William P. Spence, Eva KultermannPublisher:Cengage Learning
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,
Construction Materials, Methods and Techniques (M...
Civil Engineering
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:Cengage Learning