Practice Long term contract solution
xlsx
School
Fanshawe College *
*We aren’t endorsed by this school
Course
6010
Subject
Accounting
Date
Feb 20, 2024
Type
xlsx
Pages
10
Uploaded by SargentGuineaPig5652
Practice Long Term Contract Question (solution) Note: entries for all years, both methods are below the Contract revenue
1,500,000 2015
2016
2017
Costs incurred during the year
175,000 678,000 316,000 Estimated costs to complete the project 825,000 320,000 - Project billings invoiced during the year 150,000 700,000 650,000 Cash reciepts from customers during the year 125,000 710,000 665,000 Question 2 Provide all required entries for 2016 under the percentage of completion method. 2015
2016
2017
Costs incurred to date 175,000 853,000 Total estimated costs 1,000,000 1,173,000 Percent complete 17.50%
72.72%
Revenue to recognize 262,500.00 828,292.84 409,207 2016 Project in Progress 678,000 Cash 678,000 A/R 700,000 Billings on Contract 700,000 Cash 710,000 A/R 710,000 Construction expenses 678,000 Project in Progress 150,293 Construction Revenue 828,293 Question 3 Provide the balance sheet presentation of Accounts Receivable, Project In Progress and Billin
the completed contract method. (solution is for both methods, all three years) Completed Contract 2015
2016
2017
A/R 25,000 15,000 - Inventory Project In Progress 175,000 853,000 - Less Billings on Contract 150,000 850,000 - Net 25,000 3,000 - Question 4 Provide all required entries for 2017 using the completed contract method.
2017 Project in Progress 316,000 Cash 316,000 A/R 650,000 Billings on Contract 650,000 Cash 665,000 A/R 665,000 Construction Expense 1,169,000 Project in Progress 1,169,000 Billings on Contract 1,500,000 Contract Revenue 1,500,000 Question 5 How much revenue should be recognized in 2017 using the percentage of completion method? 409,207 as per #2 above Question 6 Provide the closing entry for Project in Progress and Billings on Contract in 2017 using the pe
completion method. 2017
Billings on Contract 1,500,000 Project in Progress 1,500,000 Full Accounting for Completed Contract 2015
201
Debit Credit Debit Project in Progress 175,000 678,000 Cash/A/P 175,000
A/R 150,000 700,000 Billings on Contract 150,000 Cash 125,000 710,000 A/R 125,000 Construction Expenses Project in Progress Billings on Contract Contract Revenue Full Accounting for % completion 2015
201
Debit Credit Debit Project in Progress 175,000 678,000 Cash/A/P 175,000 A/R 150,000 700,000 Billings on Contract 150,000 Cash 125,000 710,000 A/R 125,000 Construction Expense 175,000 678,000 Project in Progress 87,500 150,293 Contract Revenue 262,500 Billings on Contract Project In Progress
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
solution.
2,015 175,000 87,500 262,500 ngs for 2016 under % of Completion 2015
2016 2,017 A/R 25,000 15,000 - Inventory Project In Progress 262,500 1,090,793 - Less Billings on Contract 150,000 850,000 - Net 112,500 240,793 -
ercentage of 16
2017
Credit Debit Credit 316,000 678,000 316,000
650,000 700,000 650,000 665,000 710,000 665,000 1,169,000 1,169,000 1,500,000 1,500,000 16
2017
Credit Debit Credit 316,000 678,000 316,000 650,000 700,000 650,000 665,000 710,000 665,000 316,000 93,207 828,293 409,207 1,500,000 1,500,000
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Practice Long Term Contract Question
Contract revenue
1,500,000 2015
2016
2017
Costs incurred during the year
175,000 678,000 316,000 Total costs incurred to date
175,000 853,000 1,169,000 Estimated costs to complete the project
825,000 320,000 - Total estimated cost of the project
1,000,000 1,173,000 1,169,000 Project billings invoiced during the year
150,000 700,000 650,000 Cash reciepts from customers during the year
125,000 710,000 665,000 Question 1
How much revenue should be recognized in 2016 under the completed contract method? Nothing Question 2
Provide all required entries for 2016 under the percentage of completion method. Question 3
Provide the balance sheet presentation of Accounts Receivable, Project in Progress and Billings on Contract for 2016 under the completed contract method. Question 4
Provide all required entries for 2017 using the completed contract method. Question 5
How much revenue should be recognized in 2017 using the percentage of completion method? Question 6
Provide the closing entry for Project in Progress and Billings on Contract in 2017 using the percentage of completion method. Solutions
Q1
Zero! - under the completed contract method revenues and expenses are not recognized until the final year when the contrct is complete
Q2
dr
PIP - Project in Progress 678,000 cr Cash/AP 678,000 - to record the construction expenses for the year
dr
AR 700,000 cr BOC Bank of Canada 700,000 - to record the progress billings for the year
dr
Cash 710,000
cr AR 710,000 - to record the cash receipts for the year
dr
Construction expenses 678,000 dr
PIP 150,293 cr Construction revenue 828,293 - to recognize revenues and expenses for the year
ROUGH WORK
% complete =
Total costs incurred TO DATE Most recent estimate of the TOTAL COST OF THE PROJECT = 853,000 1,173,000 = 72.7%
Revenue Recognition = (% complete * Total Contract Revenue) - Revenue Prev Recognized
= 72.7% * 1,500,000 - 262,500 = 828,293 Hey! We need the revenue previously recognized in 2015! So let's calculate it…..
% complete 2015 =
Total costs incurred TO DATE Most recent estimate of the TOTAL COST OF THE PROJECT = 175,000 1,000,000 = 17.5%
= 17.5% * 1,500,000 - 0
= 262,500 Q3
Current Assets
x AR
15,000 x PIP
853,000 x Less; BOC
850,000 x Net investment in project
3,000 x Q4
dr
PIP 316,000 cr Cash/AP 316,000 Revenue Recog 2015 = (% complete * Total Contract Revenue) - Revenue Prev Recognized
- to record the construction expenses for the year
dr
AR 650,000 cr BOC 650,000 - to record the progress billings for the year
dr
Cash 665,000 cr AR 665,000 - to record the cash receipts for the year
dr
BOC 1,500,000 cr Construction Revenue 1,500,000 - to record the construction revenue for the project
dr
Contrcustion costs 1,169,000 cr PIP 1,169,000 - to record the construction expenses for the project
Q5
% complete =
Total costs incurred TO DATE Most recent estimate of the TOTAL COST OF THE PROJECT = 1,169,000 1,169,000 = 100.0%
Revenue Recognition = (% complete * Total Contract Revenue) - Revenue Prev Recognized
= 100.0% * 1,500,000 - 1,090,793 = 409,207 Q6
dr
BOC 1,500,000 cr PIP 1,500,000 - to record the cash receipts for the year
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
2015 revenue
Related Documents
Related Questions
Problem 1 - Percentage of completion
ABC Co. Uses the percentage of completion method to account for its construction contracts. Information on a recently completed contract with a
fixed contract price of P9,100,000 is shown below:
2021
2022 2023
Costs incurred to date
2,000,000 6,300,000
?
Profit recognized each year 250,000 1,550,000 400,000
Requirement:
Compute for the balance of the following
A. Cost Incurred during 2023
B. Cost Incurred to date 2023
arrow_forward
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,860,000. The project began in 2021 and
was completed in 2022 Data relating to the contract are summarized below:
2021
$ 372,000 $1,899,00e
1,488,eee
524,000
318,eee
2022
Costs incurred during the year
Estimated costs to complete as of 12/31
Billings during the year
Cash collections during the year
2,336,800
2,542, 000
Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue
over time occording to percentege of completion.
2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 ssuming this project does not qualify
for revenue recognition over time.
3. Prepare a partial balance sheet to show how the information related to this contract would be presented ot the end of 2021
assuming Nortel recognizes revenue over time according to percentege of completion.
4. Prepare a partial…
arrow_forward
May I please get solutions step by step
arrow_forward
None
arrow_forward
s
arrow_forward
Assume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below:
2024
2025
Costs incurred during the year
$ 316,000
$ 1,700,000
Estimated costs to complete as of 12/31
1,264,000
0
Billings during the year
400,000
1,660,000
Cash collections during the year
290,000
1,770,000
Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion.
Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.
arrow_forward
ABC Co. entered into a long-term construction contract for 3 years. Contract price agreed was P8,300,000. The outcome of the contract was estimated reliably. The
following data were ascertained for the contract:
Percentage of completion
Estimated costs to complete
How much is the costs of construction for 2022?
O 7,920,000
Ⓒ6,240,000
O 8,957,500
O 6,467,500
2021
30%
P 3,920,000
2022
82.5%
P 1,680,000
arrow_forward
SMC entered into a long-term construction contract for 3 years. Contract price agreed was P4,150,000. The
outcome of the contract was estimated reliably. The following data were ascertained for the contract:
December 31, 2021
December 31, 2022
Percentage of completion
30%
82.5%
Estimated cost to complete
1,960,000
840,000
1. What is the total cost incurred in year 2022?
С. 1,680,000
D. 3,120,000
A. 4,073,750
В.
840,000
2. The realized gross profit (loss) in year 2022 is
A. 650,000
B. 405,000
C. (. 245,000)
D. (1,055,000)
3. What is the construction cost of sales for year 2022?
С. 3,233,750
D. 4,478,750
A. 3,960,000
В. 3,120,000
4. What is the construction-in-progress as of 2022?
А. 3,423,750
C. 2,065,000
В. 3,310,000
D. 2,470,000
arrow_forward
Assume Avaya contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below:
2024
2025
Costs incurred during the year
$ 376,000
$ 2,265,000
Estimated costs to complete as of 12/31
1,504,000
0
Billings during the year
535,000
1,810,000
Cash collections during the year
500,000
1,845,000
Question: Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.
arrow_forward
Current Attempt in Progress
Blossom Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Bridgeport Structures
Ltd. The contract is a non-cancellable fixed-price contract for $10.2 million. The following data pertain to the construction period (all
figures in thousands).
Costs for the year
Estimated costs to complete
Progress billings for the year (non-refundable)
Cash collected for the year
Show Transcribed Text
Percent complete
2023
2023
45 %
$4,230
5,170
2024
Ĵ
5,170
600
3,905 4,595
3,445 4,645 2,110
2025
500
Using the percentage-of-completion method, calculate the percentage complete for each year of the contract. (Round answers to 0
decimal places, e.g. 52%.)
2024
-0-
1,700
94 %
2025
100 %
arrow_forward
Do not give image format
arrow_forward
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below:2018 2019Costs incurred during the year $ 300,000 $ 1,575,000Estimated costs to complete as of 12/31 1,200,000 –0–Billings during the year 380,000 1,620,000Cash collections during the year 250,000 1,750,000Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortelrecognizes revenue over time according to percentage of completion
arrow_forward
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below:
2021
2022
Costs incurred during the year
$
356,000
$
2,135,000
Estimated costs to complete as of 12/31
1,424,000
0
Billings during the year
475,000
1,760,000
Cash collections during the year
415,000
1,820,000
Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion.2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time.3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming Nortel recognizes revenue over time according to…
arrow_forward
The total contract price of the project is P 1,200,000. This was constructed as follows:
Year Cost for the year Completion as of the year
2016 P 432,000 60%
2017 P 184,250 85%
2018 P 103,750 100%
The net income to be reported in 2018 under percentage of completion is –
arrow_forward
This problem has subparts that still need to be answered
Assume Avaya contracted to provide a customer with Internet infrastructure for $2,350,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below:
2024
2025
Costs incurred during the year
$ 328,000
$ 1,830,000
Estimated costs to complete as of 12/31
1,312,000
0
Billings during the year
436,000
1,690,000
Cash collections during the year
341,000
1,785,000
Required:
Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion.
Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time.
Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time…
arrow_forward
Entity 2 entered contracts with two separate customers on 1 January 2022. The following information relates to these two contracts for 2022.
A B
£’000 £’000
Total contract price 40,000 40,000
Costs incurred to date 12,000 12,000
Anticipated further costs to completion
18,000 18,000
Cumulative progress billings invoiced 10,000 10,000
Cumulative progress billings received 8,000 8,000
Only contract A’s performance obligation is satisfied over time. Entity 2 is using the input method to determine the percentage of completion. Show how these two contracts should be presented in Entity 2’s financial statements for 2022.
arrow_forward
Current Attempt in Progress
During 2023, Sunland Corporation started a construction job with a contract price of $3.50 million. Sunland ran into severe technical
difficulties during construction but managed to complete the job in 2025. The contract is non-cancellable. Under the terms of the
contract, Sunland sends billings as revenues are earned. Billings are non-refundable. The following information is available:
(a)
2023
2024
2025
Costs incurred to date
$500,000 $1,750,000
$3,400,000
Estimated costs to complete
2,625,000
1,750,000
-0-
- Your answer is partially correct.
Calculate the amount of gross profit that should be recognized each year under the percentage-of-completion method. (Enter
negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
Gross profit/(loss)
$
2023
2024
-100,000.00
$
2025
$
100000
द
arrow_forward
4SMC entered into a long-term construction contract for 3 years. Contract price agreed was P4,150,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract:December 31, 2021December 31, 2022Percentage of completion30%82.5%Estimated cost to complete1,960,000840,0001.What is the total cost incurred in year 2022?
1.What is the total cost incurred in year 2022?
A.4,073,750 C. 1,680,000.
B.840,000. D. 3,120,000
2.The realized gross profit (loss) in year 2022 is
A.650,000. C. (. 245,000)
B.405,000 D. (1,055,000)
3.What is the construction cost of sales for year 2022?
A.3,960,000. C. 3,233,750
B.3,120,000. D. 4,478,750
4.What is the construction-in-progress as of 2022?
A.3,423,750. C. 2,065,000
B.3,310,000. D. 2,470,000
arrow_forward
please help with calculation
arrow_forward
Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of $4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable.
2023
2024
2025
Costs to date (12/31)
$1,017,000
$2,928,960
$4,576,500
Estimated costs to complete (12/31)
3,051,000
1,647,540
0
Progress billings during the year
968,000
2,418,000
1,134,000
Cash collected during the year
817,000
1,897,000
1,806,000
The revised estimates for the bridge contract are as follows.
2023 Original Estimates
2024 Revised Estimates
Contract price
$4,520,000
$4,520,000
Estimated total cost
4,068,000
4,576,500*
Estimated gross profit
$452,000
Estimated loss
$(56,500)
*$2,928,960 + $1,647,540
(a1)
Under the percentage-of-completion method, calculate…
arrow_forward
Please do not give solution in image format thanku
arrow_forward
SMC entered into a long-term construction contract for 3 years. Contract price agreed was P4,150,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract: December 31, 2017 December 31, 2018Percentage of completion 30% 82.5%Estimated cost to complete 1,960,000 840,000
1. What is the total cost incurred in year 2018?A. 4,073,750 C. 1,680,000B. 840,000 D. 3,120,000
2. The realized gross profit (loss) in year 2018 isA. 650,000 C. (. 245,000)B. 405,000 D. (1,055,000)
3. What is the construction cost of sales for year 2018?A. 3,960,000 C. 3,233,750B. 3,120,000 D. 4,478,750
4. What is the construction-in-progress as of 2018?A. 3,423,750 C. 2,065,000B. 3,310,000 D. 2,470,000
arrow_forward
Evans Construction, Inc. experienced the following construction activity in 2018, the first year of operations.
Cash Cost Estimated
Total Billings Collections Incurred Additional
Contract through through through Costs to
Contract Price 12/31/18 12/31/18 12/31/18 Complete
X €260,000 €170,000 €155,000 €182,000 € 63,000
Y 330,000 125,000 125,000 105,000 252,000
Z 233,000 233,000 198,000 158,000 -0-
€823,000 €528,000 €478,000 €445,000 €315,000
Each of the above contracts is with a different customer, and any…
arrow_forward
None
arrow_forward
Construction costs:
2020: $100,000
2021: $186,000
2022: $464,000
Estimated Costs to Complete:
2020: $400,000
2021: $464,000
2022: $0
Total Contract Price: $700,00O
Assuming this company uses the percentage of completion method,
how much Gross Profit/Loss will the company recognize in 2021?
O $464,000
O $(90,000)
O $(22,000)
O $50,000
arrow_forward
Construction costs:
2020: $100,000
2021: $186,000
2022: $214,000
Estimated Costs to Complete:
2020: $400,000
2021: $214,000
2022: $0
Total Contract Price: $700,000
Using the completed contract method, how much
Gross Profit/Loss will the company recognize in 2022?
O $100,000
O $20,000
O $200,000
O 214,000
arrow_forward
i need the answer quickly
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Related Questions
- Problem 1 - Percentage of completion ABC Co. Uses the percentage of completion method to account for its construction contracts. Information on a recently completed contract with a fixed contract price of P9,100,000 is shown below: 2021 2022 2023 Costs incurred to date 2,000,000 6,300,000 ? Profit recognized each year 250,000 1,550,000 400,000 Requirement: Compute for the balance of the following A. Cost Incurred during 2023 B. Cost Incurred to date 2023arrow_forwardAssume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,860,000. The project began in 2021 and was completed in 2022 Data relating to the contract are summarized below: 2021 $ 372,000 $1,899,00e 1,488,eee 524,000 318,eee 2022 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2,336,800 2,542, 000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time occording to percentege of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 ssuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented ot the end of 2021 assuming Nortel recognizes revenue over time according to percentege of completion. 4. Prepare a partial…arrow_forwardMay I please get solutions step by steparrow_forward
- Nonearrow_forwardsarrow_forwardAssume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: 2024 2025 Costs incurred during the year $ 316,000 $ 1,700,000 Estimated costs to complete as of 12/31 1,264,000 0 Billings during the year 400,000 1,660,000 Cash collections during the year 290,000 1,770,000 Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.arrow_forward
- ABC Co. entered into a long-term construction contract for 3 years. Contract price agreed was P8,300,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract: Percentage of completion Estimated costs to complete How much is the costs of construction for 2022? O 7,920,000 Ⓒ6,240,000 O 8,957,500 O 6,467,500 2021 30% P 3,920,000 2022 82.5% P 1,680,000arrow_forwardSMC entered into a long-term construction contract for 3 years. Contract price agreed was P4,150,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract: December 31, 2021 December 31, 2022 Percentage of completion 30% 82.5% Estimated cost to complete 1,960,000 840,000 1. What is the total cost incurred in year 2022? С. 1,680,000 D. 3,120,000 A. 4,073,750 В. 840,000 2. The realized gross profit (loss) in year 2022 is A. 650,000 B. 405,000 C. (. 245,000) D. (1,055,000) 3. What is the construction cost of sales for year 2022? С. 3,233,750 D. 4,478,750 A. 3,960,000 В. 3,120,000 4. What is the construction-in-progress as of 2022? А. 3,423,750 C. 2,065,000 В. 3,310,000 D. 2,470,000arrow_forwardAssume Avaya contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: 2024 2025 Costs incurred during the year $ 376,000 $ 2,265,000 Estimated costs to complete as of 12/31 1,504,000 0 Billings during the year 535,000 1,810,000 Cash collections during the year 500,000 1,845,000 Question: Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.arrow_forward
- Current Attempt in Progress Blossom Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Bridgeport Structures Ltd. The contract is a non-cancellable fixed-price contract for $10.2 million. The following data pertain to the construction period (all figures in thousands). Costs for the year Estimated costs to complete Progress billings for the year (non-refundable) Cash collected for the year Show Transcribed Text Percent complete 2023 2023 45 % $4,230 5,170 2024 Ĵ 5,170 600 3,905 4,595 3,445 4,645 2,110 2025 500 Using the percentage-of-completion method, calculate the percentage complete for each year of the contract. (Round answers to 0 decimal places, e.g. 52%.) 2024 -0- 1,700 94 % 2025 100 %arrow_forwardDo not give image formatarrow_forwardAssume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below:2018 2019Costs incurred during the year $ 300,000 $ 1,575,000Estimated costs to complete as of 12/31 1,200,000 –0–Billings during the year 380,000 1,620,000Cash collections during the year 250,000 1,750,000Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortelrecognizes revenue over time according to percentage of completionarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education