Standard Actual Cost per Unit Cost per Unit Direct materials: $ 5.40 Standard: 1.80 feet at $3.00 per foot. Actual: 1.80 feet at $3.30 per foot.. Direct labor: $ 5.94 Standard: 0.90 hours at $18.00 per hour. Actual: 0.92 hours at $17.50 per hour Variable overhead: Standard: 0.90 hours at $5.00 per hour. Actual: 0.92 hours at $4.50 per hour . 16.20 16.10 4.50 4.14 Total cost per unit. $26.10 $26.18 Excess of actual cost over standard cost per unit......... $0.08

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 1EA: Steeler Towel Company estimates its overhead to be $250,000. It expects to have 100,000 direct labor...
icon
Related questions
Topic Video
Question

Basic Variance Analysis; the Impact of Variances on Unit Costs

Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May.

The production superintendent was pleased when he saw this report and commented: “This $0.08 excess cost is well within the 2 percent limit management has set for acceptable variances. It’s obvious that there’s not much to worry about with this product.”

Actual production for the month was 12,000 units. Variable overhead cost is assigned to products on the basis of direct labor-hours. There were no beginning or ending inventories of materials.

Required:

1. Compute the following variances for May:

a. Materials price and quantity variances.

b. Labor rate and efficiency variances.

c. Variable overhead rate and efficiency variances.

2. How much of the $0.08 excess unit cost is traceable to each of the variances computed in (1) above.

3. How much of the $0.08 excess unit cost is traceable to apparent inefficient use of labor time?

4. Do you agree that the excess unit cost is not of concern?

Standard
Actual
Cost per
Unit
Cost
per Unit
Direct materials:
$ 5.40
Standard: 1.80 feet at $3.00 per foot.
Actual: 1.80 feet at $3.30 per foot..
Direct labor:
$ 5.94
Standard: 0.90 hours at $18.00 per hour.
Actual: 0.92 hours at $17.50 per hour
Variable overhead:
Standard: 0.90 hours at $5.00 per hour.
Actual: 0.92 hours at $4.50 per hour .
16.20
16.10
4.50
4.14
Total cost per unit.
$26.10
$26.18
Excess of actual cost over standard cost per unit.........
$0.08
Transcribed Image Text:Standard Actual Cost per Unit Cost per Unit Direct materials: $ 5.40 Standard: 1.80 feet at $3.00 per foot. Actual: 1.80 feet at $3.30 per foot.. Direct labor: $ 5.94 Standard: 0.90 hours at $18.00 per hour. Actual: 0.92 hours at $17.50 per hour Variable overhead: Standard: 0.90 hours at $5.00 per hour. Actual: 0.92 hours at $4.50 per hour . 16.20 16.10 4.50 4.14 Total cost per unit. $26.10 $26.18 Excess of actual cost over standard cost per unit......... $0.08
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College