Evaluate the below statement according to the estimation of activity duration tools, write the number of the correct statement inside the box. Makes use of group intelligence to determine the activity duration, Scaling up or down the analogous estimate. Choose. Choose. Expert Judgment The Delphi Technique Analogous Estimation Bottom-up estimating Three-point Estimating Parametric Estimation More accurate to analogous, Scaling up or down the analogous estimate.
Q: The critical path in a project is the sequence of activities that:a. has the shortest time.b. has…
A: d. None of these statements is correct.
Q: Given a project with three paths and their corresponding path lengths: A-B-C: 25 days, A-D-F: 15…
A: Given in the question - Given a project with three paths and their corresponding path lengths:…
Q: To obtain reasonable assurance about the completion of the project within the timeline, the best…
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: hy do you believe that timetable conflicts are the most common source of conflict on projects? What…
A: A timetable conflict in the workplace is when you have two tasks or events vying for your time and…
Q: Discuss possible causes for change in projects and their budgets and/or schedules. Any reference…
A: A project would include several factors from different sectors and each factor contribute to the…
Q: C) For reducing the duration of the project by one week, the activity that should be crashed first…
A: Below is the solution:-
Q: Suppose you are appointed as project manager of a construction company. Company wants you to…
A: 1.) The sequence of tasks is called the project and it is completed to achieve an outcome. It has a…
Q: Briefly describe 'Parkinson's Law' and 'Murphy's Law'. One sentence each. Then briefly in 3-6…
A: A project plan is the series of tasks that are supposed to control the project execution and…
Q: Discuss the many types of real-time scheduling tools that the group can use for the project.
A: A tool that delivers schedule component terms, descriptions, structural connections & structures…
Q: The use of probability curves to describe a project estimate helps to deal with: Your answer: The…
A: Estimation is an important skill required by many professionals. Estimates as probability…
Q: Which of the following statements is correct for Activity G's schedule? Activity G has a slack time…
A: A project schedule network diagram shows the tasks that are to be performed in the defined sequence.…
Q: The effect of scope creep is a major cause of delays on most software development project. As the…
A: Scope creep refers to the continuous and uncontrollable growth changes in the system or the project…
Q: Which statement best describes the difference between the "early bird" and the "balancing act" time…
A: The early bird and balancing act styles are two forms of time management used in the accomplishment…
Q: a. Using the normal times for each activity, what is the earliest date you can complete the project?…
A: A project schedule network diagram shows the sequence of the tasks that are performed to complete a…
Q: he of the research project should be displayed in a schedule format, with each of the process shown…
A: The answer of thus question is needs.
Q: Which of the following statements is correct with respect to slack time?a. The slack time of an…
A: Slack time in any production unit is the time available between various steps of a project. In other…
Q: Compare and contrast the traditional and agile project management approaches to time, cost and scope…
A: Project management is the management in which different types of knowledge are required to provide…
Q: unit of time used to develop the activity duration
A: activity duration indicating the time required to complete a task in a given work breakdown…
Q: Which of the following statement(s) about project vs routine work is(are) true? i. In 2019. Disney…
A: Projects are the temporary assignments that the business carries on to facilitate the organization,…
Q: Without effective collaboration, a project may suffer from the silo effect, meaning that one team…
A: Project collaboration allows whole teams to work concurrently through the wholeness of the process.…
Q: Which one is NOT one of the three time estimates used with PERT? a) Optimistic time b) Most…
A: The program (or project) evaluation and review technique (PERT) is a statistical tool used in…
Q: Select the process to which this situation can be related to, where The Project manager finds that…
A: The project manager is the responsible person who takes care of all reasonable steps necessary to be…
Q: When an activity has to be crashed, the following have to beconsidered:a) the inherent risks…
A: Crashing referred to the schedule which means to apply additional resources to the critical path…
Q: Which of the following choices is not one of the driving forces behind the increasing demand for…
A: Project managemnt involves managing a soecific product, or a project of a company for its…
Q: Suppose that you are assigned to a construction project which is planned to be build as early as…
A: Activity Estimated duration (weeks) Immediate Predecessors Immediate Predecessors A 2 B…
Q: Which of the following statements is correct with respect to an AON graph of a project?a. In an AON…
A: The right answer is B. In an AON graph, the activities are on the nodes of a graph. It is a method…
Q: The management and oversight of scope modifications within the project has an impact on the…
A: In project management, a scope tells us how a project will function and perform based on the goals…
Q: What is the correct process for setting up a recurring project for the same client? A. Create a…
A: A project is defined as a sequence of tasks that performed in specific time and cost constraints to…
Q: To obtain reasonable assurance about the completion of the project within the timeline, the best…
A: The project completion time is the maximum time taken by the activities to complete the project.
Q: Explain the difference between a project that has a fixed delivery day and one that has a fixed…
A: A project (or program) is any endeavor, done independently or cooperatively and possibly including…
Q: Suppose that you are assigned to a construction project which is planned to be build as early as…
A: A Gantt chart:It is a project management mechanism helping in the outlining & scheduling of the…
Q: You are managing a software development project. Only 35% of the work has so far been completed,…
A: behind schedule over budget
Q: Evaluate the below statement according to the estimation of activity duration tools, write the…
A: Project estimation techniques are described as the process of determining the rough approximation,…
Q: Evaluation process in the project management is use to observe and determine the score of the…
A: Project evaluation - It is about to check the working of the project. The term is used to check the…
Q: Which of the following statements is correct with respect to describing a Gantt chart?a. In a Gantt…
A: A Gantt outline is a project management tool aiding the arranging and planning of undertakings, all…
Q: Explain the difference between a project that has a fixed delivery day and one that has a fixed…
A: Fixed delivery date Fixed limit on resource usage It can be vary from the resource level which is…
Q: A recent IBM study of 585 mobile app developers and managers found that only one-third of mobile…
A: The universe of mobile applications sees new improvements consistently. Business visionaries are…
Q: Define Project Integration Management and the key components that make up Project Integration…
A: Project integration management is the coordination of all components of a task. This incorporates…
Q: For a given activity, the: most optimistic time to complete the project is 8, the most pessimistic…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: Should a project team wait until the end of a project to document its lesson learned?
A: Yes, the project team has to wait until the end of a project to document its lesson learned.
Q: What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and…
A: Given data is
Q: For projects that are complicated and more factors can influence the duration, reasonably costly.…
A: As per the given two statement-
Q: Which of the following is a source of qualitative information available to project managers? Project…
A: Qualitative information refers to the information which describes the quality and characteristics of…
Step by step
Solved in 2 steps
- Create a Group Control System Step 1. From into groups of three to five students. Each group will assume that another student group has been given an assignment of writing a major paper that will involve research by individual group members that will be integrated into the final paper. Each group member has to do his or part. Step 2. Your assignment is develop a list of rules and identify some statistics by which to control the behavior of members in that group. Brainstorm and discuss potential to govern member behavior and consequences for breaking those rules. Step 3. First, select the five rules that you think are most important for governing group member behavior. Consider the following situations that rules might cover; arriving late for a meeting: missing a meeting: failing to complete a work assignment; disagreements about desired quality of work; how to resolve conflicts about paper content; differences in participation , such as one person doing all the talking and someone else talking hardly at all; how to handle meetings that start late; the use of an agenda and handling deviations from the agenda; and any other situation that your group a cover. Step 4. Now consider what statistics could be developed to measure the behavior and outcome of the group pertaining to those five rules. What kinds of things could be counted to understand how group is performing and whether members are the following rules? Step 5. Discuss the following questions. Why are rules important as a means of control? What are the advantages and disadvantages of having many rules (hierarchical control) versus few rules (decentralized control) for a student group? How can statistics help a group ensure? appropriate behavior and a high-quality product? Step 6. Be prepared to present your conclusions to the Class.Suppose you are the director of human resources and responsible for planning your company's holiday party You decide to create a survey to gather some information that you think will be helpful in making the party a big success. Write one question for each of the following data types that you think would be helpful in planning the party. Quantitative continuous question: Quantitative discrete question:Qualitative binary question:Qualitative nominal question:Qualitative ordinal question:Why is it problematic to find the most useful numbers/statistics in football? Select all that apply 1 Football is younger than baseball, so good measures have not been found yet 2 Many football positions are dependent on other players, so it is hard to evaluate their own contribution to the win 3 Football is more complicated than baseball or basketball 4 Football season contains less games than in hockey or basketball; this inexperience leads to inconsistency of measures
- The HRM (Human Resource Management) Department of an organization administers a behavioralprofile test to measure the capabilities of individuals under consideration for employment. The testresults were analyzed manually by experts appropriate for the positions to be filled. Results aredivided into three categories: candidate style, candidate values and candidate thought preferences.Due to the large number of applicants, the many locations of the company and the high level ofexpertise required for the analysis, it was very difficult to execute a quality analysis in a timelymanner. To overcome these problems an expert system was developed which includes elevenknowledge bases.The basic objective of the system is to assess the candidate’s directional initiative, potentialperformance problems, and supervision effectiveness. Analysis of an average applicant, which takesan hour when it is done manually, can be performed in about five minutes when supported by anexpert system. The system is…Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 1 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (b) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)Job satisfaction (When you first read about this exercisebreak plan in Chapter 23, you did not have an inferencemethod that would work. Try again now.) A companyinstitutes an exercise break for its workers to see if it willimprove job satisfaction, as measured by a questionnairethat assesses workers’ satisfaction. Scores for 10 randomlyselected workers before and after the implementation ofthe exercise program are shown in the table.a) Identify the procedure you would use to assess theeffectiveness of the exercise program, and check to seeif the conditions allow the use of that procedure.b) Test an appropriate hypothesis and state yourconclusion.c) If your conclusion turns out to be incorrect, what kindof error did you commit? WorkerNumberJob Satisfaction IndexBefore After1 34 332 28 363 29 504 45 415 26 376 27 417 24 398 15 219 15 2010 27 37
- Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 9 13 B Web scraping 6 10 12 C Testing A, B 1 1 1 (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) This answer has not been graded yet. (b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) (d)…For the survey questions below: 1) Identify the problem with each survey question (lack of simplicity, double-barreled question, loaded question, or negative wording); 2) briefly explain why the question has that problem 3) rewrite the question to reduce the problem and make it a better survey question. a) Do you feel that assiduous students are more likely to graduate from college b) Do you disagree with the mayor’s policy on retirement pensions? c) Do you think that strong academics and varied social opportunities are priorities in choosing a college? d) Do you think that overtaxing our vulnerable elderly is a heartless thing to do?Opportunity-win ratio =wins/opportunities (4) Select best answer.
- Define the following:. 1. Leniency Error2. Central Tendency Error3. Strictness Error4. Halo Error5. Proximity Error6. Contrast Error7. Recency Effect9 A survey can provide insight about why a certain demographic makes a particular decision. True FalseDetermine the type of business analytics for the following scenarios. A. Imagine you are a meteorologist. You have to foretell the weather for the next two weeks by analysing the data from the satellites. Here, you have to apply advanced statistical, information software, or operations research methods to identify predictive variables and build predictive models. Discuss in detail which type of business analytics will be suitable for this scenario.