DreamInflate is a balloon manufacturing company. Balloon manufacturing consists of seven work stations, each performing a single step as indicated in the table below. There are five workers manned for the seven work stations as shown. Assume the workers are paid $15 per Worker Task Sequence Processing Time (secs/balloon) Task Dye production Electrocharging Dipping (Cold and Hot) Mortar Dipping Balloon inflation and delaltexing Vulcanization Inspection/Testing 1 30 w1 2 20 3 35 W2 4 25 W3 30 W4 45 W5 7 40 hour. Each balloon pack is sold for $6 and has a variable cost of $1. The company has fixed costs of $200 per hour. There is more demand than the overall production system can provide. Based on the information provided, answer the following questions: • What is the cost of direct labor for balloons? · How much profit does DreamInflate make every hour? (note that the cost of direct labor is also a variable cost). What would the profit of DreamInflate be if the variable costs were 10 percent lower?
Q: a) The efficiency of the assembly line with 5 workstations shown in the figure chosen above=…
A:
Q: Calculate the average time required to produce one piece per hour if there are five machines with…
A: Given data is Number of machines = 5 Machining time per piece = 0.6 hours Servicing time per piece =…
Q: Donut Love makes hand made artisan donuts in several locations throughout New Hampshire,. Assume…
A: Step Number of parallel stations/Resources Processing time for each resource (min/unit) Prep 1 30…
Q: Based on the narrative given, identify SIX (6) weaknesses from the above payroll processes. For each…
A: Payroll processing refers to a crcuical business function, involving to decide on the net pay that…
Q: Drivers are trained in a process with two resources (workers in each resource work independently).…
A: Given that: Drivers are trained in a number of processes = 2 Processing time of the first resource =…
Q: An automated car wash serves customers with the following serial process: pre-treat,wash, rinse,…
A: Flow rate of the process is also regarded as the throughput and it is defined as the number of flow…
Q: What single activity is the bottleneck for the entire process? B what?
A: A bottleneck is an activity which reduce the entire capacity of a system. It reduce the utilisation…
Q: Consider a process consisting of three resources. Assume there exists unlimited demandfor the…
A: Note- We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: Explain briefly five (5) important process scheduling policy factors that must be considered.
A: ANSWER: Planning of schedule Management : The planning for schedule management which outlay the…
Q: . What is the workstation cycle time? Workstation cycle time 80 seconds per unit . Balance this line…
A: Project schedule helps in calculating different values all related to the production cycle like the…
Q: Students have to change buildings between classes, which often involves walks of5 minutes or more.…
A: The correct option is B: Non-value-added time The Non-value-added time refers to the time that does…
Q: Use Johnson's Rule to sequence the following set of five jobs that require first a shearing…
A: Given data
Q: The objective of line balancing is to assign tasks to workstations in such a way that the…
A: Line balancing refers to assigning the right number of workers and machines to every assembly line…
Q: Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken,…
A:
Q: Cycle time is the longest cycle time allowed for each workstation in a line balancing to produce one…
A: The concept used here is understanding manufacturing times such cycle time, lead time, takt time…
Q: Suppose for a particular process that the bottleneck cycle time is 54 seconds, and raw processing…
A: Lead time is the lenght of time required from the start of process till its completion. Bottleneck…
Q: Clients are served in a process with two resources. The first resource has a capacity of 14 clients…
A: Given data: Capacity for the first resource = 14 client/hour Capacity for the second resource = 15…
Q: Consider a balanced line consisting of five single-machine stations with exponential process times.…
A: The term work-in-progress (WIP) is a creation and store network the executive's term describing…
Q: . Consider a four-step serial process with the number of workers at each step and processing times…
A: Bottleneck is defined as the point of congestion in the system of production which occurs when the…
Q: Compare and contrast TOC and JIT/Kanban as scheduling systems in operations planning and conrol
A: Total Quality Management (TQM) is the ongoing method of identifying and minimizing or removing…
Q: The objective of line balancing is to assign tasks to different workstations such that the…
A: The principle objective of line adjusting is to circulate the assignment uniformly absurd station so…
Q: a) Balance this operation using the shortest operation time rule and compute the efficiency of the…
A: Activity Immediate Predecessors Duration K3 - 60 K4 K3 24 K9 K3 27…
Q: The three-station work cell illustrated in the figure below has a product that must go through one…
A: Hello thank you for the question. As per guidelines, we would provide only 3 sub-parts at a time.…
Q: Loans are evaluated in a process with two resources. The first resource has a capacity of 0.33 loans…
A: In the above question the following information is given: First resource capacity is 0.33. Second…
Q: Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken,…
A: Following formula can be used to calculate implied utilization rate: Firstly, the workload needs to…
Q: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and…
A: It is commonly represented in "hours" and refers to the output capacity of employees or machinery.…
Q: Students are going through a three-step process to obtain their ID cards. Each student will first…
A: To be calculated: Time is taken to process 10 students Given values: A 3-step process Process 1 -…
Q: Mega Corp. is designing a product layout for a new electronic product. They plan to use this…
A: Any electrical equipment, appliance, material, system, or apparatus that conveys or is controlled by…
Q: 6. Assume the following process is used in production of a product. The are 3 workers in this…
A: Given data: Task A = 3 min/unitTask B = 6 min/unitTask C = 1 min/unit
Q: A process consists of 3 resources. Assume there exists unlimited demand for product, Resource 1 has…
A: Given- Processing time of Resource 1 = 6 minutes per unitProcessing time of Resource 2 = 4 minutes…
Q: a process consisting of three resources. Assume there exists unlimited demand for the product, and…
A: since we only answer up to 3 subparts, we'll answer the first 3. please resubmit the question and…
Q: Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line…
A: Performance bottlenecks can lead a generally utilitarian PC or worker to dial back to a slither. The…
Q: Loans are evaluated in a process with two resources. The first resource has a capacity of 30 loans…
A: Given, First resource capacity = 30 loans / hour Second resource capacity = 38 loans / hour Demand =…
Q: A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit…
A: Given Number of machines = 2 Production capacity of machine = 4 units/hour.
Q: Applications are scanned in a two step process with two resources. The processing time at the first…
A: For question 1: Arrival rate = 19 patients per hour Service rate = 18 patients per hour
Q: Consider a process consisting of five resources that are operated 8 hours per day. The process works…
A: Given data Number of operating hours = 8 hours per day Demand for Product A = 40 units per day…
Q: Loans are evaluated in a process with two sequential resources. The capacities of the resources are…
A: Given, Loans are utilized in a process with two sequential resources with, Capacity C1 =0.16 loans…
Q: Chairs are made in a process with a single resource. There are two types of chairs. The resource's…
A: Given - The demand and capacity for the resource - D1 = 2.3 per hour and D2 = 2.8 per hourS1 = 2 per…
Q: Four employees at a fast-food restaurant each perform one of the four activities in serving a…
A: From the above given information, Greet customer = 2 seconds Taking order = 30 seconds Processing…
Q: a) The throughput time of the new work cell is minutes (enter your response as a whole number). b)…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: (CLO-4] The standard time to perform the regular work cycle for a certain manual operation is 4…
A: Standard time = 4 mins Irregular work element's normal time = 2.25 mins PFD allowance = 15% Normal…
Q: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and…
A: Given data is Number of tasks = 9 Number of workers = 3 Task Processing time 1 60 2 70 3 25…
Q: Super Fun Industries manufactures four top-selling toys code named A-148, B-356, B-457, and C-843.…
A: Total plant capacity=16hrs×5days+8hrs=88 hrs =88×60=5280 minFor 1 unit of toy A-148 time required…
Q: Suppose for a particular process that the bottleneck cycle time is 54 seconds, and raw processing…
A: We have joined after 4 customers, hence there are a total of 5 customers in the system now
Q: 2-The process of making hotdogs involves six activities: “grind”, “mix”, “stuff”, “cook”, “peel”,…
A: a. The process capacity is directly proportional to the bottleneck. As the process capacity of…
Q: Callers are helped in a process with two sequential resources. The capacities of the resources are 1…
A: Given, Two resources which are in series. So, the lower capacity will be bottleneck. Capacity of…
Q: her line can produce a unit in 10 minutes. The bottleneck is station (just fill in a number in this…
A:
Q: Applications are scanned in a process with two resources. The first resource has a capacity of 21…
A: Given: Process Demand = 16 application/hourThe capacity of 1st resource = 21 Applications/hour The…
Q: upervisor Tom Choi at Tempe EquipmentCompany is concerned that material is not arriving aspromptly…
A: Calculate the percentage of time machinists were idle by computing the ratio of the number of…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Consider a law firm with 15 lawyers and 3 paralegals. The firm is struggling to keep up with the high demand for its services, particularly during the busy litigation seasons. It has been observed that the lawyers spend a significant amount of their time on administrative tasks that could potentially be handled by paralegals. After a careful study of the work distribution within the firm, it was determined that 35% of the activities carried out by the lawyers are administrative in nature. Given that each lawyer works 50 hours a week, please determine: (a) How many additional paralegals should the firm hire to handle the administrative tasks currently performed by the lawyers? (b) If the lawyers' time spent on administrative tasks is redirected to billable legal work, by what percentage could the firm potentially increase its billable hours?SkyChefs, Inc., prepares in-flight meals for a number of major airlines. One of the company’s products is grilled salmon in dill sauce with baby new potatoes and spring vegetables. During the most recent week, the company prepared 4,300 of these meals using 1,250 direct labor-hours. The company paid its direct labor workers a total of $11,250 for this work, or $9.00 per hour. According to the standard cost card for this meal, it should require 0.30 direct labor-hours at a cost of $8.50 per hour. Required: 1. What is the standard labor-hours allowed (SH) to prepare 4,300 meals? 2. What is the standard labor cost allowed (SH × SR) to prepare 4,300 meals? 3. What is the labor spending variance? 4. What is the labor rate variance and the labor efficiency variance?[The following information applies to the questions displayed below.] The following are the car repair shop data: TETE Ticket No. Work Ticket No. Work Ticket No. Work 1 Lube & oil 11 Battery 21 Battery Tires 2 Lube & oil 12 Tires 22 3 Brakes 13 Brakes 23 Brakes 4 Lube & oil 14 Transmission 24 Transmission Lube & oil 15 Brakes 25 Brakes Tires 16 Battery 26 Lube & oil 7 Tires 17 Brakes 27 Lube & oil 8. Brakes 18 Tires 28 Lube & oil 9. Brakes 19 Tires 29 Tires 10 Lube & oil 20 Lube & oil 30 Lube & oil
- The Holt Million Corporation’s plant manufactures two different products: X and Y. The plant has three different machines: A, B, and C. Each performs different tasks and can work on only one unit of material at a time. Details for each product are shown in the table below: Product X Y Demand Per Week 200 units 100 units Selling Price $150 $160 Machine Operation Required A, B, C B, B, C Operation Times in Minutes 20, 15, 15 15, 15, 15 Raw Materials Needed RM-1, RM-2 RM-2, RM-3 Raw Materials Costs RM-1 = $40/unit, RM-2 or RM-3 = $20/unit Each product uses raw materials with costs as shown in the above table where the processing times and the machine required for each operation are also shown. Each machine is available 4,800 minutes per week. There are no system foul-ups. Demand is deterministic (i. e., no uncertainty). Operating expenses, including labor (but excluding raw materials) total $12,000 per week. Assuming…The Holt Million Corporation’s plant manufactures two different products: X and Y. The plant has three different machines: A, B, and C. Each performs different tasks and can work on only one unit of material at a time. Details for each product are shown in the table below: Product X Y Demand Per Week 200 units 100 units Selling Price $150 $160 Machine Operation Required A, B, C B, B, C Operation Times in Minutes 20, 15, 15 15, 15, 15 Raw Materials Needed RM-1, RM-2 RM-2, RM-3 Raw Materials Costs RM-1 = $40/unit, RM-2 or RM-3 = $20/unit Each product uses raw materials with costs as shown in the above table where the processing times and the machine required for each operation are also shown. Each machine is available 4,800 minutes per week. There are no system foul-ups. Demand is deterministic (i. e., no uncertainty). Operating expenses, including labor (but excluding raw materials) total $12,000 per week. Assuming…A manufacturing company produced first unit in 15:00 hours and dollar 2,50,000 worth of material, equipment usage, and supplies. The second unit took 13 hours and used dollar two lakh worth of materials, equipment usage and supplies. Labour is dollar 15 per hour. Determine the total production cost for additional 10 units after the second unit was completed round the final amount to nearest integer
- A small electronic company assembles power supplies for use in bread maker, cake mixer and food processor. It wants to set up an assembly line to make its operations more efficient and plan to use line balancing with the incremental utilization heuristic. The demand for power supplies is 200 per hour, and the productive time per hour is 52 minutes. The following table provides details on its operation (with time in minutes): Time to perform task 0.56 0.34 0.11 0.09 0.43 0.22 0.62 0.35 0.21 0.57 0.33 Tasks that must Task A immediately precede A A A F G B,C D E H. F,G H K 1,J (a) Compute the cycle time. (b) Compute the theoretical minimum number of workstations. (c) Draw a precedence diagram for the production line to show precedence relationships.A business company has the following capacity per month based on the following: 30 working days per month; 1 shift operation at 8 hours per shift; 30 minutes break per shift per employee ABC company produces bicycles and has the following Capacities per process. Frame Welding: 60 bikes per hour per machine Painting: 20 bikes per hour per worker Assembly: 50 bikes per hour per worker Inspection: 100 bikes per hour per worker What can be observed from the system if the demand for the month is 5,000 bikes?ABC Solutions is a traditional company in a textile industry with a combined workforce of 150 staff. Due to increased levels of competition, this company is now increasingly finding it difficult to compete – especially as the larger companies seem to be a little more innovative, agile and responsive to client requirements. Management have noticed that staff, especially the highly skilled ones, are now leaving the company to seek work elsewhere (in these larger companies). This has meant appointing new staff and undertaking a considerable amount of re-training to replace those that have left the company. Apart from impacting on core business operations, ABC Solutions has started witnessing a drop in its profit margin. Given this position, senior management at ABC Solutions have decided to implement a performance measurement tool (PMT) that would allow them to align the strategic, management and operational requirements of the business. They are therefore considering the adoption of the…
- Charles Lackey operates a bakery in Idaho Falls, Idaho. Because of its excellent product and excellent location, demand has increased by % in the last year. On far too many occasions, customers have not been able to purchase the bread of their choice. Because of the size of the store, no new ovens can be added. At a staff meeting, one employee suggested ways to load the ovens differently so that more loaves of bread can be baked at one time. This new process will require that the ovens be loaded by hand, requiring additional manpower. This is the only thing to be changed. The bakery currently makes loaves per month. The pay will be $ per hour for employees and each employee works 160 hours per month.Charles Lackey can also improve the yield by purchasing a new blender. The new blender will mean an increase in his investment. This new blender will mean an increase in his costs of $ per month, but he will achieve the same new output (an increase to ) as the change in labor…Joliana is a human resources professional with Odd Objects Company. Her primary responsibility is during the fall is to prepare the customer care center for their seasonal rush. She is tasked with a goal of filling 100 customer support positions by Halloween. She screens candidates and forwards potential fits to the manager of customer care. Jollana is playing a key role in which of the following processes? Multiple Choice human capital shadowing recruiting mentoring inh specificationA TV factory plans to add production lines for its new product and plans to produce as many as 200 units per hour. The production process, production time, and the production process to continue the next production process are described in the table below: (1 day = 8 working hours) Production Process Production Time (s) The production process that follows the next production according to the list below A 12 - B 15 A C 8 A D 5 B,C E 20 D Based on the data above. a. What is the cycle time for the production of the new product? (note: in seconds)b. What is the minimum number of workstations?