Draw a network diagram showing the linkage between these activities from start to finish. For the diagram, each activity should be labelled alphabetically ie. A, B, C… etc. PERT Formula: TE = (O + 4T + P) / 6  TE = Pert Expected Time Duration, O = Optimistic estimate, P = Pessimistic estimate, T = Most Likely (Typical) estimate Activity Predecessor Optimistic Most Likely Pessimistic Duration Duration in Weeks   A — 2 3 4   B — 4 5 7   C B 1 2 3   D C & E 0.5 1 1.5   E B 0.5 1 1.5   F C 2 3 4   G F 2 3 4

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question

 Draw a network diagram showing the linkage between these activities from start to finish. For the diagram, each activity should be labelled alphabetically ie. A, B, C… etc.

  • PERT Formula:
  • TE = (O + 4T + P) / 6 
  • TE = Pert Expected Time Duration,
  • O = Optimistic estimate,
  • P = Pessimistic estimate,
  • T = Most Likely (Typical) estimate

Activity

Predecessor

Optimistic

Most Likely

Pessimistic

Duration

Duration in Weeks

 

A

2

3

4

 

B

4

5

7

 

C

B

1

2

3

 

D

C & E

0.5

1

1.5

 

E

B

0.5

1

1.5

 

F

C

2

3

4

 

G

F

2

3

4

 

 

Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,