Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 5,600 units of product were as follows:   Standard Costs Actual Costs Direct materials 7,300 lb. at $5.50 7,200 lb. at $5.40 Direct labor 1,400 hrs. at $16.20 1,430 hrs. at $16.50 Factory overhead Rates per direct labor hr.,     based on 100% of normal     capacity of 1,460 direct     labor hrs.:       Variable cost, $2.80 $3,880 variable cost     Fixed cost, $4.40 $6,424 fixed cost Each unit requires 0.25 hour of direct labor. Required: a.  Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Direct materials price variance $fill in the blank 1   Direct materials quantity variance fill in the blank 3   Total direct materials cost variance $fill in the blank 5

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter9: Standard Costing: A Functional-based Control Approach
Section: Chapter Questions
Problem 30P: Algers Company produces dry fertilizer. At the beginning of the year, Algers had the following...
icon
Related questions
icon
Concept explainers
Topic Video
Question

Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 5,600 units of product were as follows:

  Standard Costs Actual Costs
Direct materials 7,300 lb. at $5.50 7,200 lb. at $5.40
Direct labor 1,400 hrs. at $16.20 1,430 hrs. at $16.50
Factory overhead Rates per direct labor hr.,  
  based on 100% of normal  
  capacity of 1,460 direct  
  labor hrs.:  
    Variable cost, $2.80 $3,880 variable cost
    Fixed cost, $4.40 $6,424 fixed cost

Each unit requires 0.25 hour of direct labor.

Required:

a.  Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct materials price variance $fill in the blank 1
 
Direct materials quantity variance fill in the blank 3
 
Total direct materials cost variance $fill in the blank 5
 

b.  Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct labor rate variance $fill in the blank 7
 
Direct labor time variance fill in the blank 9
 
Total direct labor cost variance $fill in the blank 11
 

c.  Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Variable factory overhead controllable variance $fill in the blank 13
 
Fixed factory overhead volume variance fill in the blank 15
 
Total factory overhead cost variance $fill in the blank 17
 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

b.  Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct labor rate variance $fill in the blank 7
 
Direct labor time variance fill in the blank 9
 
Total direct labor cost variance $fill in the blank 11
 

c.  Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Variable factory overhead controllable variance $fill in the blank 13
 
Fixed factory overhead volume variance fill in the blank 15
 
Total factory overhead cost variance $fill in the blank 17
 
Solution
Bartleby Expert
SEE SOLUTION
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning