Consider the Work Breakdown Structure of this project. Immediate Activity Duration (days) Predecessor(s) A none 6 B A 13 A 13 B 5 C, D 14 F C, D 15 G E, F 8 At a minimum, how long will this project take (in days)?
Q: There are three general approaches to anti-corruption training and education in MNC’s. List the…
A: Corruption can be stated as the abuse of power for private gain. It is one thing that not supposed…
Q: 3. A product whose total work content time = 50 minutes is to be assembled on a manual production…
A:
Q: What is the best decision alternative under Maximax criterion? (Provide complete decision table…
A: Given data:
Q: a. What is the EOQ? (Enter your response rounded to the nearest whole number.) and (Enter your…
A: EOQ stands for economic order quantity. It is a company's optimal order quantity that undervalues…
Q: The Winston Company has four distribution centers (A, B, C, and D) that require 40,000, 60,000,…
A: Given data is
Q: ustify the requirement for a trained project manager to oversee complicated tasks.
A: A project manager is an individual who controls supervises and monitors the project members and…
Q: Mattress Wholesalers, Inc. is constantly trying to reduce inventory in its supply chain. Last…
A: Given data: LAST YEAR CURRENT YEAR Cost of goods sold 7.52 millions 8.62…
Q: 1. A catering company prepared and served 300 meals at an anniversary celebration last week using…
A: Productivity is the relationship between the total output and total inputs of the process.
Q: Q10) Which of the following motivation for M&A is related to Cisco’s many numbers of acquisition?…
A: Note- Hi! Thank you for the question As per the honour code, We’ll answer the first question since…
Q: Explain what kind of costs you evaluate when you do the trade-off in transportation mode analysis.
A: Transportation mode analysis (TMA) is used to evaluate alternative delivery methods, including…
Q: Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field…
A: Note: - Since we can answer only up to three subparts we will answer first three subparts(a, b, and…
Q: Solve the table using the Least-cost and Vogel Method: (ii) $10 $4 $2 8 $2 $3 $4 5 $2 $0 $1 6 7 6 6
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: Wikipedia, free encyclopedia, mission is to collect and develop educational information and make it…
A: Wikipedia is a platform at which we can access free data and knowledge without paying any costs for…
Q: A cement manufacturing company will produce 24 tons per week. The demand for the cement is 6 tons…
A: Given data Annual demand (D) =6 tons per week ×52 weeks in a year =312 tonnes of units per year…
Q: 1. A businessman needs 5 cabinets, 12 desks, and 18 shelves cleaned out. He has two part-time…
A: Note: - Since it is specified to answer question number 2 we will answer question 2 here. If answer…
Q: 1. Following table shows costs to produce each unit of a product. Unit Number Cost 1" K 2 6400.00…
A: a.
Q: When undertaking performance testing, what are the most important criteria to keep in mind?
A: Performance testing:- Performance testing can be divided into two parts: load testing and stress…
Q: Is it possible to convey the concept of optimality in dynamic programming?
A: Yes, it is far feasible to bring the idea of optimality into dynamic programming. Dynamic…
Q: LP PROBLEM: Ozark Farms uses at least 800 lb. of special feed daily. The special feed is a mixture…
A: Given data is
Q: During the next production period, The Diego Garcia Furniture Company is considering producing…
A: As per the sensitivity report, the allowable decrease for objective coefficient (Profit) for…
Q: Maximize C = 13x + 3y subject to 12x + 14y ≤ 21 15x + 20y ≤ 37 and x ≥ 0, y ≥ 0. What is the…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: aintain an existing supply chain, wh
A: The distribution of a product from its place of origin to its point of consumption is referred to as…
Q: Describe the ideal exterior store design for Clothing Store
A: The exterior of any store is an external part of the store that protects the store from outside…
Q: You work for the Brad's Nailer Company which manufactures two types of nailers: a pneumatic model…
A: Decision variables: X1 = Units of Pneum. model X2 = Units of Cordless model Objective function:…
Q: Determine if project management software can assist you in better controlling the expenditures of…
A: Project management is the management in which different types of skills and knowledge are required…
Q: What is the difference between Time series data and Cross sectional data. What are the examples of…
A: Data are facts or kind of information that is often numeric. Data is collected to gain information…
Q: What are the most critical considerations to bear in mind while doing performance testing?
A: Performance testing means verifying and validating the performance of a system or application. In…
Q: hould be represented as a source/sink or as a process is difficult to make.
A: The sources and sinks are located outside of the system.
Q: Product design has been identified as the real key to world- competitive business. The steps in the…
A: Product design is the procedure when a novel product is formed to sell to customs. The phases of the…
Q: What is the significance of a systems analyst's job in a project?
A: System analysts job is very important position in the organisation because it maintains,implements…
Q: For this queestion, findd the correct match for each item in the first column labeled 'Concept' to…
A: A manufacturing process in which a business builds or makes a product. It can be a difficult…
Q: QUESTION 13 Before he died, Steve Jobs asked the employees to consider the demands of their fellow…
A: Internal stakeholders are the stakeholder which are present within the internal organisation and are…
Q: Tell us why it's so critical to integrate product requirements with production procedures.
A: Product requirement refers to the quality of a output which a firm wants from its production units…
Q: HW 5 Q6 Solidtronic Incorporated an original equipment manufacturer (OEM), has a product…
A: Given data: T=71 x= 66 or 76 L(x) = $600
Q: Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new…
A: Given, The flow matrix and distance matrix. The distance matrix can be mirrored to get the other…
Q: A certain reagent is created to test for an infectious disease. The test has an accuracy rate of p =…
A: Given : Accuracy rate of p = 90%, People are infected q = 5%
Q: Given the following activity network: A1 A3 activity A1 takes 5 weeks, A2 takes 10 weeks, and A3…
A: Given dataActivity A1 = 5 weeksActivity A2 = 10 weeks Activity A3 = 7 weeks
Q: What is the Material Master specification in SAP ERP and why is it one of the most complex types of…
A: All material master records recorded in the SAP system are material master data. Based on material…
Q: When integrating suppliers, what are the best practices to follow?
A: Suppliers are very important and has a great role in firms sucess because they supply the scarce…
Q: What is the effect on the cost of quality to the customer when in an agreement with a supplier to…
A: Cost of quality or called (COQ) is described as a process that authorizes an organization to specify…
Q: 6. Leaky Pipe, a local retailer of plumbing supplies, faces demand for one of its SKUs at a constant…
A: Given data is Demand(D) = 17000 units Holding cost(H) = $2 per unit Order cost(S) = $5 Lead time(L)…
Q: operations Manageme A contract of sale is distinct from other types of contracts because it has two…
A: A contract of sale is a contract in which a seller agrees to sell a specified quantity of a product…
Q: what factors aided Rockwater in it's smooth switch to the balance scorecrd?
A: A balanced scorecard is a performance management report which provides feedback on internal business…
Q: QUESTION 15 Calculate the minimum value of 9x + 5y subject to the following constraints: x+ y> 22 x…
A: Given- Min 9x+5y Subject to constraint- x+y≥22 x+2y≥29 2x+y≥27 x≥0 y≥0
Q: What is lean management? And can it be a beneficial strategy for a young entrepreneur?
A: Today, managing a company is not an easy task. Many different activities are conducted and managed…
Q: Ann decided to hired Dionne Richards to be her assistant given the exigencies of this particular…
A: Given: identified resources=10 Kimberley Sharpe who would continue the set of activities started by…
Q: What was one national security policy the United States established during the Covid-19 pandemic?
A: Covid-19 pandemic has resulted in huge loss to human life. It presented an extraordinary challenge…
Q: Plan production for a four-month period: February through May. For February and March, you should…
A: Production planning is important because it provides a productive production process based on…
Q: reflection on the very fast construction projects and its advantages and disadvantages.
A: Fast construction projects are the projects which have very less scheduled timings and which are…
Q: The annual demand for cups is 2.3 million, the annual carrying cost per box of cups is $1.90, and…
A: We would calculate the EOQ and total annual cost of all alternatives and the alternative with lowest…
Step by step
Solved in 2 steps with 1 images
- O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,2. a) The activity shown in Table Q2 (a) are processes carried out in a mechatronic company. Based on the table provided, (i) Determine the Critical Path and Project Duration to complete the process. ii. Activity F cannot start immediately after activity C. The delay is expected to be 7 days. Determine by stating the possible problem, Critical Path and Project Duration to complete the process.4,4 The late start time for activity c is: 04 b, s None of the above 14 7 O11 0.3 d5 f. 2 h, I
- (a) What is Work Breakdown Structure (WBS)? Explain in light of a building construction project while clearly give emphasis on task, duration and resources. (b) Explain the five different proformas of Planning Commission of Pakistan used in project life cycle phases. (c) Explain the following. 1. Present worth analysis 2. Effective interest rate . please solve this perfectly. subject: : Project Planning, Management & Engineering Economics 3. Project life cycleon in OMGT 1013 x (1) Facebook - usl-tuguegarao.neolms.com/student take_quiz_assignment/display/23380965?part=14&r ODE 606 ÖMGT 1013 Item 14 of 78 Refer to the given information below for a particular project. Activity Immediate Predecessors Time (weeks) A None 2 BD 4. 3 E F Compute the slack time for activity D A. LLGiven the data for a project in table Q3, using the following assumptions: 1. 8 hours as working day 2. The company will work all days. 3. Maximum number of workers available per day is 6 4. Activities cannot be break down 5. Budget will distributed equally per day, except for activities (B, H and L), the payment will be after two days of working: means that the first payment will be at the end of day2, then day four and so on. 6. They estimate that the work will starts on the first of November 2017 Develop a report containing the followings: Date of finish BAD O GYEK 1. 2. Early start and Slack time for each activity 3. Resource histogram 4. Cumulative Budget baseline curve 5. Interpret the final report co Table Q3 Duration (Hrs) No of Workers Budget Activity predecessor A None 48 12000 64 32000 C 16 10000 32 4. 12000 B,C 32 8000 B,C 16 6000 G B,C 16 4 10000 H. 64 16000 3. 16 4000 32 1 12000 K 32 3 16000 H. 48 1 12000 Total Budget of RM150000
- You have been assigned a project and in your preliminary planning you have developed table 2 below, it outlines eight activities (A to H) that must be completed. For each activity you have obtained the estimated duration, cost per day and the prior task(s). Activity A B с D E F G H Z Duration (days) 3 4 12 6 16 15 Cost/week ($) 2500 6000 3000 10000 15000 10000 7 8 0 Prior Tasks None B, D C, E E, F,G 0 All *Assume that there are five (5) workdays in each week Table 2 2000 2500 A A, B A, B D Using the information provided: a) Create a network diagram for the project. b) Construct a Gantt Chart for the project. c) Determine the minimum time in which the project can be completed. 1Activity A B CDEFG 3. You have been appointed as the project leader of a project to be undertaken by your company. You have identified the following tasks and made the time estimates for each task as listed in the table below: с Preceding "from" activity A A A B,C C,D,E F Succeeding "to" activity B,C,D E E F F G Estimated duration work days) 3 5 3 10 8 14 7 a) Use the above table to construct a project network diagram. b) Determine the critical path for the project and its duration.A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Optimistic Time (hr) Most Probable Time (hr) 4 4 0.5 2 3 5 5 Сл 1 3 7.5 Pessimistic Time (hr) 6 6 1.5 10 9 Naturally, the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. (a) Construct the PERT/CPM network for this problem.
- please help, project management. I need part D,Eand 2 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach? Make sure to document any cited…PERT/CPM HOMEWORK (MOD 10) In the table below, you will see activities and times associated with each activity. Review the PowerPoint slides in Module 10 , before you start this assignment. Task Preceding Tasks to (optimistic) tm (most likely) tp (pessimistic) A NONE 2 3 10 B NONE 2 3 4 C A 1 2 3 D A 4 6 14 E B 4 5 12 F C 3 4 5 G D,E 1 1 7 1.) Draw the network using the table above. Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance? 4.) What is the probability that it would be in more than 14 days? Show ALL of your work. *The circle diagram picture is just an example of how it should look it is not apart of the problem in the chart#3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.