Before answering the following questions, you must draw the arrow diagram, rectangles, network calculations, and the project diagram, the details of which are shown in the table below. Time (week) Activity Dependency Resource b a 2.5 1.5 2 2.5 6 3 1 3 2 А, В B 1.5 2.5 2 0.5 1.5 1 3 3 3 D, E C, F, G С, G 7 3.5 3 5 1.5 2.5 2 18- How long will the project be if the duration of the activity G becomes eight weeks 21 12 17 19 16 All options are incorrect EN N2124 42 ABCDEFGH-
Q: For the activities shown in the table using PERT, draws the network diagram and determine the…
A: Find the Duration calculations below:
Q: The following table provides the information necessary to construct a project network diagram and…
A: Project crashing is a process which reduces the total duration using additional costs. Here, we can…
Q: 4. Schedules and activities of a project are shown below. Answer the questions. Activity…
A: A) The CPM chart is as follows: The critical path is: A-D-E-H-I-L
Q: The nine activities A to I whích make up a project are subject to the following precedence…
A: Disclaimer- Since you have posted a question with multiple sub parts , we will solve first three sub…
Q: Below is the first set of activities (Phase I) in constructing a new house, the respective time…
A:
Q: The Figure 1 below shows the activities on the nodes, while the table shows the normal time, crash…
A: There are two separate paths. The duration of the paths is: Start–A–B–F–End = 18 days…
Q: The Laurenster Corporation is getting into the construction business. A list of activities and their…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: A) Draw the Gantt Chart B) Draw the Network Diagram C) Identify and draw the critical path using the…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: 1- The network below represents a project being analyzed by Critical Path Methods. Activity…
A: Since you have submitted questions with multiple subparts, as per guidelines we have answered the…
Q: snip
A: Note: Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: A project has been defined to contain the following activities, along with their time estimates for…
A: The Critical path diagram of the given activities as follows -
Q: The activity details and their predecessors are given below along with their activity times.…
A: The construction of the network is very important to understand the flow of activities in the…
Q: The conditions and pert times for constructing a network diagram are given below. -Creation…
A: Given data is
Q: ID Immediate Time (weeks) Predecessor A 6 B. 4 3. D. A, B, C 7 4. F D 2 H. ID Cost by week (in…
A:
Q: For the following sitution draw a PERT network, and determine the following: Critical path…
A: The Program Evaluation and Review Technique (PERT) can be defined as a technique in which an…
Q: Draw the AON project network using the following information: How long would it take to complete…
A: The diagram of the AON project network is shown below
Q: Norton Industries is installing a new computer system. The activities, the activity times, and the…
A: Crashing an activity is basically adding more assets toward an activity so it tends to be finished…
Q: 5) Draw the Network and do the analysis Using the information in Table 1, assuming that the project…
A: Note: - Since we can answer only up to 3 subparts, we will answer sub part i, ii, and iii for…
Q: (a) What is the critical path? (b) How long will it take to complete this project? (c) Can…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: The activities described by the following table are given for the Howard Corporation in Kansas:…
A: Given data is
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: a.
Q: The detail of the direct cost for project XYZ are given in Table 1. Table 1 Details for Project XYZ…
A: Given data is
Q: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Below is the network diagram from a project: B(2) D(5) A(2) F(3) C(5) E(3) What is the slack for…
A: A project network is the visual representation of the project activities and their respective…
Q: 12. Given the following network project where the times are in days: Task Normal Crash Normal Crash…
A: Given data: TASK NORMAL TIME CRASH TIME NORMAL COST CRASH COST IP A 2 1 200 300 - B 3 1 100…
Q: Q1,Draw the network. Q2,what is the critical path Q3,how many weeks will it take to complete the…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Given the activities whose sequence is described by thefol lowing table, draw the appropriate…
A: Critical path refers to the stage sequences, that require maximum time for the project completion.
Q: A project has the following activities, precedence relationships, and activity duration. Draw the…
A: Given that: Activity Immediate Predecessor(s) Duration (Weeks) A None 18 B A 8 C B 6 D…
Q: Time (weeks) Immediate Time (weeks) Immediate Activity Predecessor(s) Activity Predecessor(s) a a A…
A: Estimated activity periods are not guaranteed when doing Critical Path calculations. This date is…
Q: The Laurenster Corporation is getting into the construction business. A list of activities and their…
A: Expected time of each activity, Activity to tm tp te=to+4⋅tm+tp6 σ2=(tp-to)62 A…
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: Consider the below project information for questions 1-4. Activity Immediate Duration (days)…
A: Answer: A project consists of different activities. The project mentioned in the question is having…
Q: A project has the following activities, with specified precedents and expected durations (in hours).…
A: A network diagram is a diagram that shows the visual form of the project activities and their…
Q: 1. A new application development project at NeuProd, Inc. consists of the following activities:…
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: Using the network diagram constructed in Problem 1,(a) Calculate the completion time for the…
A: The completion time of the project can be calculated as below:
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: This was a three part question. Bartelby helped me get A and B. The picture for Part A is the…
A: In the question, we have table data, this table data includes Information like activity ID, activity…
Q: 2. A network consists of the activities in the following list. Times are given in days. Activity…
A: Given data is
Q: Construction of a building is based on the followingCPM network:a. Draw the network for this project…
A: "Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Task time estimates for the modificat ion of an assembly line at Jim Goodale's Carbondale, Illinois,…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: Please help me answer parts 3. and 4. of this question if not all of them. Thank you
A: Forward Pass:Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)Early Finish =…
Q: The following CPM/PERT network represents a small project with 4 activities labelled A through D.…
A: Given data is
Q: What is the slack time for activity A? 7 5 3 0
A: Formula:
Q: 3. Activities of a project are summarized in the following table. Activity Immediate Duration…
A: a) The network diagram is as follows: The critical path is: B-F-H The project completion time is 24…
Q: The network dlagram and task times for a project are shown below. A2 A4 A5 A3 Task Duration (days)…
A: Using Forward Path, find Early Start of the activity = Early Finish of predecessor activity Early…
Q: A student club plans on holding a campus-wide event at the end of the semester. The activities that…
A: Given that: Duration Immediate Activity (weeks) Predecessor A 2 -- B 3 A C 1 A D 3…
Q: For the activity times and network model below, What is the expected completion time? ________ What…
A: Here is the network diagram with activity & time duration :
Q: Q1: A project consisting of the following activities: ML KTJIH GFE D CB A K J HE GF D.C D.C D.C A BB…
A:
Step by step
Solved in 2 steps with 3 images
- ++ Earned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: Table 2 No 1 2 3 Type Cumulative Budgeted Cost (CBC) Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) TOTAL RM 64,000 68,000 54,000 100,000 Percentage 64.0 68.0 54.0 100.0 a) With the aid of a typical S-curve diagram, draw and explain the four cost-related measures such as TBC, CBC, CAC and CEV to analyses the overall project cost performance.What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL TIME (DAYS) CRASH TIME (DAYS) 5 4 ACTIVITY Design (A) Wiring (8) Chip install (C) 7 5 3 4 7 2 2 4 NORMAL COST 300 900 500 CRASH COST 1,100 1,200 350 975 575 Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $1,875 (enter your response as a whole number). IMMEDIATE PREDECESSOR(S) 1,300 1,650 A, B сThe expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 10
- B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of workRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity ABCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B A, D C E, F Time (days) 4 5 3 10 4 6 10
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity D. Activity B is connected to activity E. Activity C is connected to activity F. Activity D is…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a). Develop a project network. (b) Develop an activity schedule. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F (c) What are the critical activities? (Enter your answers as…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity E. Activity C is connected to activity D. Activity D is…
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop an activity schedule. What are the critical activities? (Enter your answers as a comma-separated list.) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost? (A, B, C, D, E) = (e) Develop an activity schedule for the crashed project. Activity EarliestStart LatestStart…You are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?