a) Draw the network diagram. What is the project completion time? What is the critical path? b) Crash activity B by one day. What is the new project completion time?
Q: The following table provides the information necessary to construct a project network diagram and…
A: Project crashing is a process which reduces the total duration using additional costs. Here, we can…
Q: A2 A4 A5 A3 Task Duration (days) 3 A1 3 A2 A3 1 A4 A5 days What is the late finish time for activity…
A: Using the Forward Path Early Start of the activity = Early Finish of predecessor activity Early…
Q: B. What is the expected project completion time? 7 weeks 8 weeks 9 weeks 6 weeks C. Which are the…
A: In this question, I would construct the Gantt chart based on the given Activity ID, Activity…
Q: a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d.…
A: Find the Slope calculations below:
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: A) Draw the Gantt Chart B) Draw the Network Diagram C) Identify and draw the critical path using the…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: a. Construct the network. b. How long will it take to finish the project? c.. What is the critical…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Ql: For activitices shown in table below, find the new time of project after updating, if the…
A: Given data is
Q: a. Draw the project network diagram. b. What completion date would you recommend?
A: Below is the solution:-
Q: 1. Draw the project network 2. What is the expected time for activity B? 3. What is the variance for…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Norton Industries is installing a new computer system. The activities, the activity times, and the…
A: Crashing an activity is basically adding more assets toward an activity so it tends to be finished…
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: A project network diagram is the visual representation of the project activities and their durations…
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given Information:
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: a.
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: lease complete the ES, EF, LS, LF, and slack for the project below. Activity Description
A: Early start (ES) indicates the earliest time of the beginning of the activity. Early finish (EF)…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: a.
Q: Consider the following data for a project to install a newserver at the Northland Pines High School:…
A: The critical path method, or critical path analysis, refers to an algorithm which is used for…
Q: a. Determine the expected time (t,) for each activity. 5. Identify the critical path(s) c. What is…
A: Answer is as below:
Q: Given the activities whose sequence is described by thefol lowing table, draw the appropriate…
A: Critical path refers to the stage sequences, that require maximum time for the project completion.
Q: The Omega department is planning to bid on large project for the development of a new communication…
A:
Q: a) Construct a Gantt chart using MS Project 2016 b) Assuming the default 5-day workweek, calculate…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: Example: - 02) Activities of a project with estimates of activity times are listed below. Activity…
A: In order to calculate the expected time, the following formula is used. Expected time =Optimistic…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: The Scott Corey accounting firm is installing a new computer system. Several things must be done to…
A: The method of analyzing the set of activities related to the project of the company is known as the…
Q: Build a PERT Analysis for a 3-month project with 6 activities (A to F) and 5 nodes
A: The PERT Method (or Program Evaluation and Review Approach) is a standard network analysis…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: a.
Q: able Activities Name A E Predecessor A А, В D C, E Time (Days) 7 9 12 9.
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: a. Draw a network diagram and determine the expected project completion time b. What is the…
A: Below is the solution:-
Q: a) Develop a network diagram for the project. Identify the critical path. b) If the company would…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Activity Predecessor Time(weeks) A 8 B A 6 4 D E A 11 F B 3 D, E, F 1 Using Table A, what is the…
A: Network Diagram,
Q: PM.58 Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities…
A: Forward Pass:Early Start (ES) = Maximum (or Highest) EF value from immediate Predecessor(s)Early…
Q: A. (5 points) Draw AON diagram of the project, including activity durations. B. (4 points) Based on…
A:
Q: Answered all given questions as below. Value for A and B will be determined by your unique id as per…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(a, b,…
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A:
Q: 2. Consider the data given in the following table and give what is asked. Immediate Normal Time…
A: Find the Given details below: Activity Predecessor Original duration (NT) (Days) Original cost…
Q: Below matrix shows one of the important data used in project management, identify the name of the…
A: The matrix shown in the question is named as RACI Chart or RACI Matrix. The RACI Chart or RACI…
Q: Given the activities whose sequence is describedby the following table, draw the appropriate…
A: Draw the path
Q: a) Draw the project network using AON. b) Identify the critical path. c) What is the expected…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1. Determine the amount of slack in each of a proiect's activities (presented below), and identify…
A: Formula:
Q: 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 2. Determine the amount of slack in each of a project's activities (presented below), and identify…
A:
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: Construct a network diagram b. State the expected finish time and critical path of the project
A: A network diagram is a graphical representation of a project which visualizing the activity…
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 9 7 7 6 5 4 6 4 9 6 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ NORMAL COST 200 800 600 1,100 1,200 CRASH COST 300 875 675 1,300 1,875 IMMEDIATE PREDECESSOR(S) (enter your response as a whole number). A, B CConsider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time. Table 1: Crash Cost Table Activity Immediate Predecessor Normal Duration (days) Normal Cost ($) Crash Duration (days) Crash Cost ($) A --- 5 50 3 150 B --- 4 40 2 200 C B 7 70 5 250 D A, C 2 20 1 50 E A, C 5 125 1 525 F B 10 80 7 290 G D 7 50 3 250 H E, F 6 60 3 180 Reduce the project duration to minimum duration and calculate the cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.CRASHING AND COST PLAN Problem 3 From the following data perform crashing the project. Activity Ti7me in Weeks Cost Cost per Week Normal Crash Normal Crash 1-2 (A) 1-3 (B) 2-4 (C) 3-4 (D) 3-5 (E) 4-6 (F) 5-6 (G) 5-7 (H) 6-7 (1) 10,000 7,000 3,200 10,000 5,200 14,000 8,100 9,600 8,000 2 3 2,000 4,000 2,000 8,000 2,000 10,000 6,000 6,000 4,000 2,000 600 400 500 800 4 12 8 3 2,000 700 1 11 7 900 10 1,000 ТОTAL 33 18 P44,000 P75,100 Can we finish the project in 18 weeks instead of 33 weeks at a cost of less than P75,100 indirect cost? 87꼬735꺼e
- What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL CRASH TIME (DAYS) TIME (DAYS) 8 7 7 6 6 6 9 6 NORMAL COST 400 1,100 700 900 1,200 CRASH COST 550 1,300 800 1,250 1,950 IMMEDIATE PREDECESSOR(S) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $ whole number). A, B C (enter your response as aWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Time Activity Time (days) (days) AB А C D E 67555 5 BCD w 55 с 4 2 Activity A E 3 Normal Cost $800 $300 $600 $750 $1,200 Immediate Total Cost with Crashing Predecessor(s) $1,100 $500 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) $650 $1,500 $1,650 - Each Activity Should be Reduced BY (days) A CIFS233 Donell Consulting recently completed an IT training platform implementation with a public firm. The project concluded after the completion of a testing, piloting and sign-off from the project stakeholders. Though completed, the project manager was reviewing their notes, in which they listed all the important occurrences that were recorded during various project phases: ● The pilot of the training platform is about to begin, and the COO of the firm has informed the project team that they want an additional 1000 staff trained and included, and the firm will be increasing budget accordingly. The new systems analyst replacement just found an issue with the way in which the training platform is recording information inputted from users. Apparently, it does note read or collate all the metadata produced during user inputs, and only considers metadata that leads to a complete sequence of inputs. This is going to cause issues in how we record the users' activities as the client wants to…
- Image of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Normal Time Crash Time Cost to Crash Immediate Activity (weeks) (weeks) ($ per week) Predecessor(s) А 5 4 200 None В 9 8. 300 None C 4 200 А 4 2 250 A 3 3 В F 3 С, D G 3 1 150 D, E 7 350 F 4 4 G Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) Time according to schedule (weeks) Activity Activity A В G C H ENormal Time Problem 1 You are the manager of a project to improve a billing process at your firm. The following table contains the data you will need to conduct crashing of the project duration. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12. Activity Immediate Predecessor(s) Crash Time (weeks) Normal (Direct) Cost Crash Cost (weeks) ($) ($) A 4 1 5,000 8,000 B 5 2 8,000 11,000 C A 1 1 4,000 4,000 Ꭰ B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F Ꭰ 7 6 4,000 7,000 What is the optimum choice for project duration?
- Can i get help with the question below please and thank you 16) This could be a rover, probe/satellite, manned mission, telescope, etc. This mission must be accomplished using technology that is available today (no Warp or Epstein drives) and must be accomplished within your lifetime. Your mission will not be a copy of a real mission. Constraints: ▪ Answer using the underlined subheadings at each point below (Mission Objective, Target, Instrumentation), marks will be deducted for poorly organized answers. ▪ You target must be reachable by whatever you are sending within a human lifetime (~75 years), it would be nice to visit Gliese 581c, but it is 20 light years from Earth so for now it is unreachable. What this means is that you are constrained to our solar system except for telescopes that peer into the universe or a probe getting to interstellar space. ▪ If your mission includes sending humans, then we need to estimate a reasonable limit on how far we can send humans. For our…Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?General Foundry’s project crashing data are shown below. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing? What is the crash cost per week per activity and the total cost of crashing? TIME (WEEKS) COST ($) ACTIVITY IMMEDIATE PREDECESSORS NORMAL CRASH NORMAL CRASH A — 2 1 22,000 23,000 B — 3 1 30,000 34,000 C A 2 1 26,000 27,000 D B 3 2 48,000 49,000 E C 4 2 56,000 58,000 F C 3 2 30,000 30,500 G D, E 5 2 80,000 83,000 H F, G 2 1 16,000 19,000